Data centers and new power in Arkansas
21.1 GW of new power is waiting to connect to the grid in Arkansas — 99 requests across 34 counties. That is the 22nd largest amount of any state. 58 projects are built, 315 withdrawn. Data as of 14 October 2026.
What is happening with electricity in Arkansas
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Arkansas right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Arkansas.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
472 requests ever filed
Source: the interconnection queues of every transmission provider operating in Arkansas. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 59 | 11.8 GW |
| Solar + battery | 23 | 4.0 GW |
| Wind | 8 | 2.2 GW |
| Natural gas | 3 | 1.6 GW |
| Not stated | 5 | 1.4 GW |
| Biomass | 1 | 0 MW |
Who runs the waiting list in Arkansas
Counties in Arkansas
34 with power on the waiting list
Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.
| County | Waiting | Capacity queued | Already built |
|---|---|---|---|
| Crittenden County | 7 | 1.8 GW | 400 MW |
| Mississippi County | 7 | 1.7 GW | 3.1 GW |
| Jefferson County | 4 | 1.2 GW | 114 MW |
| Jackson County | 4 | 1.2 GW | 2.1 GW |
| Calhoun County | 3 | 1.1 GW | 0 MW |
| Craighead County | 4 | 950 MW | 0 MW |
| Ouachita County | 4 | 901 MW | 0 MW |
| Phillips County | 6 | 890 MW | 200 MW |
| Hot Spring County | 2 | 875 MW | 0 MW |
| Union County | 2 | 870 MW | 600 MW |
| Lonoke County | 3 | 788 MW | 300 MW |
| Nevada County | 2 | 750 MW | 0 MW |
| St. Francis County | 3 | 680 MW | 500 MW |
| Arkansas County | 4 | 665 MW | 275 MW |
| Columbia County | 3 | 662 MW | 0 MW |
| Grant County | 3 | 640 MW | 100 MW |
| Lee County | 2 | 515 MW | 985 MW |
| Franklin County | 4 | 451 MW | 0 MW |
| Clay County | 2 | 300 MW | 0 MW |
| Sebastian County | 2 | 250 MW | 0 MW |
| Poinsett County | 2 | 240 MW | 0 MW |
| Little River County | 1 | 204 MW | 0 MW |
| Cross County | 1 | 200 MW | 405 MW |
| Chicot County | 1 | 135 MW | 250 MW |
| Woodruff County | 1 | 130 MW | 0 MW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| SPP | SPP 2028 CPP Interconnection Cluster Study (ICS) application window Definitive Interconnection System Impact Study cluster, post Order 2023 compliance. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.