TVA interconnection queue

97 interconnection requests are active in TVA, totalling 23.5 GW, as of 15 August 2026. Of the 676 requests ever filed here, 71 were built and 508 were withdrawn — a build rate of 12.3% on decided applications.

Active requests
97
of 676 ever filed
Capacity queued
23.5 GW
requested, not committed
Built vs decided
12.3%
71 built, 508 withdrawn
Median wait so far
3.4 yr
for requests still active
Median time to build
3.8 yr
request to commercial operation

Source: the TVA interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in TVA, by fuel

FuelProjectsCapacity requested
Gas2215.1 GW
Solar425.3 GW
Battery142.3 GW
Nuclear8576 MW
Hydro11188 MW

Where TVA’s queue sits

StateApplicationsCapacity pending
Tennessee32213.7 GW
Kentucky663.9 GW
Alabama1243.1 GW
Mississippi1522.8 GW
Arkansas60 MW
Georgia40 MW
North Carolina10 MW
Virginia10 MW

Largest active requests

ProjectFuelCapacityCountyStateFiled
489Gas1.7 GWRoane CountyTN2021-12
483Gas1.6 GWStewart CountyTN2021-10
620Gas1.6 GWTrousdale CountyTN2024-06
628Gas1.6 GWTodd CountyKY2024-06
257Gas1.1 GWShelby CountyTN2014-08
618Gas800 MWStewart CountyTN2024-06
622Gas800 MWTrousdale CountyTN2024-06
416Gas780 MWColbert CountyAL2020-02
417Gas780 MWMuhlenberg CountyKY2020-02
25RSC-012Gas752 MWHaywood CountyTN2025-08
25RSC-001Gas692 MWFayette CountyTN2025-07
569Gas620 MWLowndes CountyMS2023-06
401Gas593 MWHumphreys CountyTN2019-09
25RSC-011Gas528 MWMorgan CountyAL2025-08
624Gas375 MWHaywood CountyTN2024-06