Lonoke County, AR interconnection queue
3 interconnection applications are pending in Lonoke County, AR, requesting 788 MW of new generating capacity, as of 15 August 2026. 2 projects have been built here and 14 have been withdrawn since 2017.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Lonoke County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Wind | 2 | 668 MW |
| Hybrid | 1 | 120 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 2 | 300 MW | 10.5% |
| Still pending | 3 | 788 MW | 15.8% |
| Withdrawn | 14 | 2.3 GW | 73.7% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| WEST MEMPHIS EHV - KEO EHV 500.0kV | Wind | 348 MW | active | 2024-04 | MISO |
| WEST MEMPHIS EHV - KEO EHV 500.0kV | Wind | 320 MW | active | 2024-12 | MISO |
| WHITE BLUFF EHV - KEO EHV 500.0kV | Hybrid | 300 MW | withdrawn | 2024-04 | MISO |
| KEO EHV | Solar | 300 MW | withdrawn | 2025-06 | MISO |
| HOLLAND BOTTOM - KEO EHV 500.0kV | Hybrid | 300 MW | withdrawn | 2024-04 | MISO |
| KEO EHV 500 kV Substation | Solar | 250 MW | completed | 2019-04 | MISO |
| Genpower Keo 500kV | Solar | 200 MW | withdrawn | 2021-08 | MISO |
| Remington AECC to Lonoke E 115kV | Solar | 200 MW | withdrawn | 2022-09 | MISO |
| Keo 500kV | Solar | 150 MW | withdrawn | 2022-09 | MISO |
| Genpower Keo 500kV | Solar | 150 MW | withdrawn | 2021-08 | MISO |
| AECC KEO-BAUCUM 115 kV | Solar | 125 MW | withdrawn | 2022-09 | MISO |
| Taping the 'Carlisle / 3CARISLE! (338003)' to 'Screeton / 3SCREETON (338005)' 11 | Hybrid | 120 MW | active | 2022-09 | MISO |
| Genpower Keo 500kV | Solar | 110 MW | withdrawn | 2021-08 | MISO |
| REMINGTON SS - LONOKE EAST 115.0kV | Solar | 105 MW | withdrawn | 2022-09 | MISO |
| Garner SS to Seracy Price 115kV line | Hybrid | 100 MW | withdrawn | 2021-08 | MISO |
How this county ranks
Lonoke County ranks #475 of 1,607 US counties by capacity currently queued, and #10 of 34 in Arkansas.
Other Arkansas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Crittenden County | 7 | 1.8 GW |
| Mississippi County | 6 | 1.5 GW |
| Jefferson County | 4 | 1.2 GW |
| Jackson County | 4 | 1.2 GW |
| Calhoun County | 3 | 1.1 GW |
| Craighead County | 4 | 950 MW |
| Ouachita County | 4 | 901 MW |
| Phillips County | 6 | 890 MW |
Go deeper on Lonoke County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Lonoke County on the map County reports All of Arkansas