Data centers and new power in Mississippi County, AR
1.7 GW of new power is waiting to connect to the grid in Mississippi County, AR — 7 active requests. Typical wait: 1.4 years. 12 projects are built, 18 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Mississippi County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Mississippi County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Mississippi County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Mississippi County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
37 requests ever filed
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 12 | 3.1 GW | 32.4% |
| Still waiting | 7 | 1.7 GW | 18.9% |
| Withdrawn | 18 | 5.3 GW | 48.6% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 1.4 GW |
| Not stated | 1 | 200 MW |
| Solar + battery | 2 | 155 MW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| DELL EHV - NEW MADRID (AECI) 500.0kV | Solar | 500 MW | withdrawn | 2024-03 | MISO |
| DELL EHV - SAN SOUCI 500.0kV | Solar + battery | 500 MW | completed | 2021-08 | MISO |
| DELL EHV - SAN SOUCI 500.0kV | Solar + battery | 500 MW | completed | 2021-12 | MISO |
| DELL EHV - SAN SOUCI 500.0kV | Solar + battery | 500 MW | completed | 2021-12 | MISO |
| DELL EHV - SAN SOUCI 500.0kV | Solar | 500 MW | active | 2024-04 | MISO |
| Sandy Bayou | Solar | 500 MW | active | 2022-09 | MISO |
| 592 | Solar | 500 MW | withdrawn | 2023-12 | TVA |
| 593 | Solar | 500 MW | withdrawn | 2023-12 | TVA |
| 594 | Solar | 500 MW | withdrawn | 2023-12 | TVA |
| 597 | Solar | 500 MW | withdrawn | 2023-12 | TVA |
| 598 | Solar | 500 MW | withdrawn | 2023-12 | TVA |
| 599 | Solar | 500 MW | withdrawn | 2023-12 | TVA |
| Sandy Bayou | Solar | 440 MW | completed | 2021-11 | MISO |
| San Souci 500 kV Substation | Solar | 300 MW | withdrawn | 2018-03 | MISO |
| GILMORE - WILSON 161.0kV | Solar + battery | 300 MW | withdrawn | 2024-04 | MISO |
How Mississippi County compares
#227 in the US · #2 in AR
Mississippi County ranks #227 of 1,607 US counties by power waiting to connect, and #2 of 34 in Arkansas.
| County | Waiting | Capacity queued |
|---|---|---|
| Crittenden County | 7 | 1.8 GW |
| Jefferson County | 4 | 1.2 GW |
| Jackson County | 4 | 1.2 GW |
| Calhoun County | 3 | 1.1 GW |
| Craighead County | 4 | 950 MW |
| Ouachita County | 4 | 901 MW |
| Phillips County | 6 | 890 MW |
| Hot Spring County | 2 | 875 MW |
Common questions about power in Mississippi County
How long does it take to get power for a data center in Mississippi County, AR?
The median wait for a project still in the interconnection queue in Mississippi County is 1.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 12 projects in Mississippi County have reached energization and 18 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Mississippi County, AR?
1.7 GW is currently requested across 7 active interconnection requests, and 3.1 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Mississippi County, AR a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Arkansas policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Mississippi County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Mississippi County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Mississippi County on the map County reports All of Arkansas