Data centers and new power in St. Francis County, AR

680 MW of new power is waiting to connect to the grid in St. Francis County, AR — 3 active requests. Typical wait: 1.3 years. 1 projects are built, 6 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside St. Francis County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in St. Francis County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in St. Francis County right now.

680 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 544,000 homes use.
500 MW
has actually been built
1 projects switched on so far.
1.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 10%
  • Still waiting 30%
  • Withdrawn 60%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for St. Francis County.

What kind of power is asking to connect

  • Solar 88%
  • Solar + battery 12%

By capacity requested. Data as of 14 October 2026.

All the numbers

10 requests ever filed
Pending applications
3
of 10 ever filed
Capacity queued
680 MW
requested, not committed
Already built
500 MW
1 projects connected
Built vs decided
14.3%
6 withdrawn
Median wait
1.3 yr
for applications still pending
Connected capacity
203 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1500 MW10.0%
Still waiting3680 MW30.0%
Withdrawn6731 MW60.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2600 MW
Solar + battery180 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 10 by size
ProjectTypeCapacityStatusFiledQueue
West Memphis - Keo 500 kV Line TapSolar500 MWcompleted2018-03MISO
WEST MEMPHIS EHV - KEO EHV 500.0kVSolar400 MWactive2025-10MISO
BRINKLEY EAST - AECC AUBREY 230.0kVSolar200 MWactive2025-06MISO
FORREST CITY SOUTH - HUGHES 161.0kVSolar151 MWwithdrawn2024-04MISO
West Memphis-Genpower Keo 500kV Line Break (located at "CHALKBLUFFPV" 500kV POI Solar150 MWwithdrawn2022-09MISO
Hughes-Forest City South 161kv lineSolar140 MWwithdrawn2018-03MISO
Entergy Hughes - Forest City South 161 kVSolar + battery140 MWwithdrawn2022-09MISO
Moses - McCrory 161 kV Line tapSolar100 MWwithdrawn2018-03MISO
BRINKLEY EAST - AECC PALESTINE 161.0kVSolar + battery80 MWactive2025-06MISO
AECC Forrest City West 161 kV SubstationSolar50 MWwithdrawn2018-03MISO

How St. Francis County compares

#520 in the US · #13 in AR

St. Francis County ranks #520 of 1,607 US counties by power waiting to connect, and #13 of 34 in Arkansas.

CountyWaitingCapacity queued
Crittenden County71.8 GW
Mississippi County71.7 GW
Jefferson County41.2 GW
Jackson County41.2 GW
Calhoun County31.1 GW
Craighead County4950 MW
Ouachita County4901 MW
Phillips County6890 MW

Common questions about power in St. Francis County

How long does it take to get power for a data center in St. Francis County, AR?

The median wait for a project still in the interconnection queue in St. Francis County is 1.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in St. Francis County have reached energization and 6 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in St. Francis County, AR?

680 MW is currently requested across 3 active interconnection requests, and 500 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is St. Francis County, AR a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Arkansas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving St. Francis County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on St. Francis County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open St. Francis County on the map County reports All of Arkansas