Jackson County, AR interconnection queue
4 interconnection applications are pending in Jackson County, AR, requesting 1.2 GW of new generating capacity, as of 15 August 2026. 6 projects have been built here and 11 have been withdrawn since 2017.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Jackson County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Wind | 2 | 500 MW |
| Solar | 1 | 500 MW |
| Hybrid | 1 | 200 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 6 | 2.1 GW | 28.6% |
| Still pending | 4 | 1.2 GW | 19.0% |
| Withdrawn | 11 | 2.6 GW | 52.4% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV | Solar | 625 MW | completed | 2021-10 | MISO |
| INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV | Solar | 625 MW | completed | 2021-10 | MISO |
| MALLORY 161 | Solar | 500 MW | completed | 2021-11 | MISO |
| Independence (A)(500kV) to Powerline (B) (500 kV) | Solar | 500 MW | withdrawn | 2022-09 | MISO |
| Mallory 161 kV Substation | Solar | 500 MW | active | 2022-09 | MISO |
| Independence-ISES- Newport 161 KV | Solar | 500 MW | withdrawn | 2022-09 | MISO |
| Cash - Newport AB | Solar | 300 MW | withdrawn | 2022-07 | MISO |
| HOLLAND BOTTOM - INDEPENDENCE-ISES 500.0kV | Wind | 300 MW | active | 2022-09 | MISO |
| Newport Ab-Cash 161kV | Solar | 250 MW | withdrawn | 2022-09 | MISO |
| Swifton to Hoxie 161 kV | Solar | 220 MW | withdrawn | 2022-09 | MISO |
| PECAN ST - AECC BALCH 161.0kV | Solar | 200 MW | withdrawn | 2024-05 | MISO |
| INDEPENDENCE-ISES - POWERLINE ROAD 500 kV | Solar | 200 MW | withdrawn | 2022-09 | MISO |
| Taping 'Newport AB / NEWPORTSOLAR (338177)' to 'Cash / 5CASH (338171)' 161kV Lin | Hybrid | 200 MW | active | 2022-09 | MISO |
| NEWPORT | Wind | 200 MW | active | 2022-09 | MISO |
| Cash - Newport AB 161 kV Line Tap | Solar | 180 MW | completed | 2017-06 | MISO |
How this county ranks
Jackson County ranks #322 of 1,607 US counties by capacity currently queued, and #4 of 34 in Arkansas.
Other Arkansas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Crittenden County | 7 | 1.8 GW |
| Mississippi County | 6 | 1.5 GW |
| Jefferson County | 4 | 1.2 GW |
| Calhoun County | 3 | 1.1 GW |
| Craighead County | 4 | 950 MW |
| Ouachita County | 4 | 901 MW |
| Phillips County | 6 | 890 MW |
| Hot Spring County | 2 | 875 MW |
Go deeper on Jackson County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Jackson County on the map County reports All of Arkansas