Interconnection cluster window calendar — 13 windows open now

13 interconnection and large-load deadlines are open or upcoming across the seven organised markets and FERC, as of 15 September 2026. 2 of them close within sixty days. Cluster windows are annual: a missed close is a year lost, not a week.

Open or upcoming
13
next twelve months
Closing within 60 days
2
counted live in your browser
Checked against a primary source
11
of 13
No date published yet
8
listed, not guessed

Assembled by Watt Street from each authority's own tariff, order and form pages where we have checked them, and from commercial calendars and law-firm notes where we have not. Every row says which. Data as of 15 September 2026. The same calendar is available over the API and MCP, with the confidence flag on every record.

Everything open or upcoming

QueueWhat closesClosesStanding
ERCOTERCOT Production Load Schedule - Resource Entity model information submission deadline
ERCOT publishes real calendar cutoffs for submitting complete model information ahead of each network model production load.
2026-10-01confirmed source
CAISOCAISO Cluster 16 interconnection request window
Interconnection requests submitted through the GRIP portal.
2026-10-15confirmed source
ISONEISO-NE cluster request window
Cluster study under OATT Schedules 22, 23 and 25.
2026-11-19confirmed source
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
2027-01-01unconfirmed source
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

Known to be coming, no date published

These are real windows with no announced date. They are listed rather than omitted, because knowing a window exists and is unannounced is itself planning information — and because a placeholder date is something somebody would diary.

QueueWhatWhat we knowSource
ERCOTERCOT Batch 1 large load interconnection - applications not yet datedSuccessor cycle to Batch Zero under PGRR145.link
ERCOTERCOT generation interconnection — rollingNot FERC-jurisdictional.link
FERCFERC large-load show cause — stakeholder comments on RTO responsesComments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70, CAISO EL26-71, ISO-NE EL26-72).link
FERCFERC RM26-4 — generic large-load rulemakingStill at ANOPR stage.link
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before executionA standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.link
NYISONYISO cluster request windowClass Year deliverability construct plus the new cluster process.link
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application windowDefinitive Interconnection System Impact Study cluster, post Order 2023 compliance.link
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))All new large-load interconnections must carry ERCOT-controlled curtailment equipment.link

How to read the standing column

Confirmed means the date was read off the authority's own tariff, order, docket or form page, and the check itself is recorded — what was read, what was corrected, and what could not be reached. Unconfirmed means we have it from a commercial calendar, a law-firm note or trade press and have not yet made that check. Disputed means we made the check and the authority's own documents contradicted the date we held, so we withdrew it rather than leave it standing. We publish all three, labelled, because the alternative is publishing only what we have checked and leaving you unaware that the rest exists. Nothing here is legal or filing advice — read the source before you diary a date.

Put this on your own page. The counter is available as a free embed — one line of HTML, no key, and it stays right without you touching it. Get the snippet.

Found one we have wrong or missing? Email [email protected]. Corrections are published in our corrections log, including our own.