Data centers and new power in Tioga County, PA

974 MW of new power is waiting to connect to the grid in Tioga County, PA — 2 active requests. Typical wait: 0.2 years. 1 projects are built, 23 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Tioga County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Tioga County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Tioga County right now.

974 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 779,000 homes use.
22 MW
has actually been built
1 projects switched on so far.
0.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 4%
  • Still waiting 8%
  • Withdrawn 88%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Tioga County.

What kind of power is asking to connect

  • Natural gas 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

26 requests ever filed
Pending applications
2
of 26 ever filed
Capacity queued
974 MW
requested, not committed
Already built
22 MW
1 projects connected
Built vs decided
4.2%
23 withdrawn
Median wait
0.2 yr
for applications still pending
Connected capacity
126 MW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built122 MW3.8%
Still waiting2974 MW7.7%
Withdrawn232.2 GW88.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas2974 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
EVERGREEN RIDGE POWERNatural gas624 MWactive2026-07NYISO
Tioga County PowerNatural gas550 MWwithdrawn2015-04NYISO
Mansfield 115kVNatural gas500 MWwithdrawn2000-07PJM
Patriot Forge Energy CenterNatural gas350 MWactive2026-08NYISO
Tower Hill 115kVNatural gas250 MWwithdrawn2015-04PJM
Homer-Watercure 345kVWind150 MWwithdrawn2006-04PJM
Mainesburg ESSBatteries130 MWwithdrawn2020-06NYISO
Mainesburg 115 kVBatteries100 MWwithdrawn2020-03PJM
Cherry FlatsWind90 MWwithdrawn2006-06NYISO
Mansfield - Mainesburg 115 kVSolar85 MWwithdrawn2022-02PJM
Mansfield - Tower Hill 115kVWind70 MWwithdrawn2006-12PJM
Sabinsville 115 kVSolar50 MWwithdrawn2021-03PJM
Youst SolarSolar35 MWwithdrawn2022-03PJM
Blossburg #1 CT 34.5 kVNatural gas22 MWcompleted2019-09PJM
Sabinsville 34.5kVNatural gas20 MWwithdrawn2017-02PJM

How Tioga County compares

#379 in the US · #4 in PA

Tioga County ranks #379 of 1,607 US counties by power waiting to connect, and #4 of 62 in Pennsylvania.

CountyWaitingCapacity queued
York County62.9 GW
Clearfield County111.5 GW
Indiana County31.2 GW
Dauphin County3896 MW
McKean County4870 MW
Centre County5591 MW
Fayette County4310 MW
Crawford County6248 MW

Common questions about power in Tioga County

How long does it take to get power for a data center in Tioga County, PA?

The median wait for a project still in the interconnection queue in Tioga County is 0.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Tioga County have reached energization and 23 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Tioga County, PA?

974 MW is currently requested across 2 active interconnection requests, and 22 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Tioga County, PA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Pennsylvania policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Tioga County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Tioga County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Tioga County on the map County reports All of Pennsylvania