Crawford County, PA interconnection queue
6 interconnection applications are pending in Crawford County, PA, requesting 248 MW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 45 have been withdrawn since 1999.
Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Crawford County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 6 | 248 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 6 | 248 MW | 11.5% |
| Withdrawn | 45 | 2.4 GW | 86.5% |
| Suspended | 1 | — | 1.9% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Erie West 345 kV | Gas | 765 MW | withdrawn | 1999-01 | PJM |
| Edinboro South-Venango Junction 115 kV III | Battery | 204 MW | withdrawn | 2021-09 | PJM |
| Geneva 115 kV | Solar | 150 MW | active | 2021-02 | PJM |
| Edinboro South-Venango Junction 115 kV | Solar | 116 MW | withdrawn | 2019-03 | PJM |
| Edinboro South-Venango Junction 115 kV IV | Solar | 116 MW | withdrawn | 2023-03 | PJM |
| Springboro-Venango Junction 115 kV | Battery | 112 MW | withdrawn | 2020-09 | PJM |
| Geneva 115kV | Other | 96 MW | withdrawn | 2011-08 | PJM |
| Springboro-Venango Junction 115 kV | Solar | 78 MW | withdrawn | 2019-09 | PJM |
| Corry East 115kV | Wind | 70 MW | withdrawn | 2010-08 | PJM |
| Wayne 115 kV | Solar | 70 MW | withdrawn | 2019-07 | PJM |
| Wayne 115 kV | Solar | 62 MW | withdrawn | 2019-03 | PJM |
| Geneva 115 kV | Solar | 50 MW | withdrawn | 2020-01 | PJM |
| Morgan Street 115 kV | Battery | 50 MW | withdrawn | 2022-03 | PJM |
| Geneva-Franklin Tap 115 kV | Solar | 44 MW | withdrawn | 2020-03 | PJM |
| Geneva 115 kV | Solar | 44 MW | withdrawn | 2020-09 | PJM |
How this county ranks
Crawford County ranks #859 of 1,607 US counties by capacity currently queued, and #8 of 62 in Pennsylvania.
Other Pennsylvania counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| York County | 6 | 2.9 GW |
| Clearfield County | 11 | 1.5 GW |
| Indiana County | 3 | 1.2 GW |
| Dauphin County | 3 | 896 MW |
| McKean County | 4 | 870 MW |
| Centre County | 5 | 591 MW |
| Fayette County | 4 | 310 MW |
| Somerset County | 3 | 229 MW |
Go deeper on Crawford County