Cambria County, PA interconnection queue
1 interconnection applications are pending in Cambria County, PA, requesting 150 MW of new generating capacity, as of 15 August 2026. 10 projects have been built here and 33 have been withdrawn since 1997.
Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Cambria County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 1 | 150 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 10 | 2.5 GW | 22.7% |
| Still pending | 1 | 150 MW | 2.3% |
| Withdrawn | 33 | 4.1 GW | 75.0% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Hunterstown-Conemaugh 500kV | Gas | 1.1 GW | completed | 2016-10 | PJM |
| Hunterstown-Conemaugh 500kV | Gas | 1.1 GW | completed | 2014-10 | PJM |
| Conemaugh-Juniata 500kV | Unknown | 741 MW | withdrawn | 2009-09 | PJM |
| Hunterstown-Conemaugh 500kV | Gas | 550 MW | withdrawn | 2000-07 | PJM |
| Hunterstown-Conemaugh 500kV | Gas | 550 MW | withdrawn | 2000-07 | PJM |
| Cambria Slope 115 kV | Gas | 325 MW | withdrawn | 2017-09 | PJM |
| Cambria Slope 115kV | Coal | 165 MW | withdrawn | 2005-01 | PJM |
| Krayn 115 kV | Wind | 158 MW | withdrawn | 2022-03 | PJM |
| Bear Rock-Johnstown 230 kV | Solar | 150 MW | active | 2019-12 | PJM |
| Medera - Westover South 115 kV | Solar | 150 MW | withdrawn | 2023-03 | PJM |
| Krayn 115 kV | Wind | 148 MW | withdrawn | 2022-03 | PJM |
| Cambria Slope 115kV | Coal | 125 MW | withdrawn | 2004-07 | PJM |
| Carrolltown 46 kV | Wind | 113 MW | withdrawn | 2022-03 | PJM |
| Bear Rock-Johnstown 230 kV | Solar | 100 MW | completed | 2019-03 | PJM |
| Colver Power Project 115 kV | Solar | 100 MW | withdrawn | 2022-09 | PJM |
How this county ranks
Cambria County ranks #1011 of 1,607 US counties by capacity currently queued, and #15 of 62 in Pennsylvania.
Other Pennsylvania counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| York County | 6 | 2.9 GW |
| Clearfield County | 11 | 1.5 GW |
| Indiana County | 3 | 1.2 GW |
| Dauphin County | 3 | 896 MW |
| McKean County | 4 | 870 MW |
| Centre County | 5 | 591 MW |
| Fayette County | 4 | 310 MW |
| Crawford County | 6 | 248 MW |
Go deeper on Cambria County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.