Data centers and new power in Wyoming County, NY

649 MW of new power is waiting to connect to the grid in Wyoming County, NY — 3 active requests. Typical wait: 0.2 years. 7 projects are built, 20 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Wyoming County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Wyoming County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Wyoming County right now.

649 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 519,000 homes use.
452 MW
has actually been built
7 projects switched on so far.
0.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 23%
  • Still waiting 10%
  • Withdrawn 67%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Wyoming County.

What kind of power is asking to connect

  • Wind 54%
  • Batteries 46%

By capacity requested. Data as of 14 October 2026.

All the numbers

30 requests ever filed
Pending applications
3
of 30 ever filed
Capacity queued
649 MW
requested, not committed
Already built
452 MW
7 projects connected
Built vs decided
25.9%
20 withdrawn
Median wait
0.2 yr
for applications still pending
Connected capacity
534 MW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built7452 MW23.3%
Still waiting3649 MW10.0%
Withdrawn201.6 GW66.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind2349 MW
Batteries1300 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Swiss Valley Energy StorageBatteries300 MWactive2024-10NYISO
Sapphire Solar and StorageBatteries200 MWwithdrawn2021-09NYISO
Seventy Seven WindWind199 MWactive2026-07NYISO
Erie-Wyoming County SolarBatteries175 MWwithdrawn2018-12NYISO
Buffalo Rd. Wind FarmWind165 MWwithdrawn2005-02NYISO
Buffalo Rd. Wind Farm IIWind165 MWwithdrawn2005-03NYISO
Salt Rush WindWind150 MWactive2026-07NYISO
Wethersfield Windfield 115kVWind129 MWwithdrawn2005-02NYISO
Wethersfield 230kVWind126 MWcompleted2005-02NYISO
Dairy Hills Wind FarmWind120 MWwithdrawn2005-02NYISO
High Sheldon WindfarmWind112 MWcompleted2004-02NYISO
Seventy-Seven SolarSolar100 MWwithdrawn2021-02NYISO
Orangeville WindWind96 MWwithdrawn2005-04NYISO
Stony Creek Wind FarmWind93 MWcompleted2007-10NYISO
Salt Rush WindWind75 MWwithdrawn2021-02NYISO

How Wyoming County compares

#534 in the US · #19 in NY

Wyoming County ranks #534 of 1,607 US counties by power waiting to connect, and #19 of 57 in New York.

CountyWaitingCapacity queued
Suffolk County273.7 GW
Kings County83.1 GW
Orange County101.6 GW
Ulster County111.3 GW
Steuben County81.3 GW
Dutchess County71.1 GW
Nassau County21.1 GW
Genesee County4926 MW

Common questions about power in Wyoming County

How long does it take to get power for a data center in Wyoming County, NY?

The median wait for a project still in the interconnection queue in Wyoming County is 0.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 7 projects in Wyoming County have reached energization and 20 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Wyoming County, NY?

649 MW is currently requested across 3 active interconnection requests, and 452 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Wyoming County, NY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Wyoming County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Wyoming County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Wyoming County on the map County reports All of New York