Dutchess County, NY interconnection queue

5 interconnection applications are pending in Dutchess County, NY, requesting 854 MW of new generating capacity, as of 15 August 2026. 3 projects have been built here and 16 have been withdrawn since 2002.

Pending applications
5
of 24 ever filed
Capacity queued
854 MW
requested, not committed
Already built
2.2 GW
3 projects connected
Built vs decided
15.8%
16 withdrawn
Median wait
1.9 yr
for applications still pending
Connected capacity
1.4 GW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.

What is waiting in Dutchess County, by fuel

FuelProjectsCapacity requested
Battery5854 MW

Outcomes of every application filed here

OutcomeProjectsCapacityShare
Built32.2 GW12.5%
Still pending5854 MW20.8%
Withdrawn164.1 GW66.7%
Suspended00.0%

Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.

The largest projects on file

ProjectFuelCapacityStatusFiledQueue
Cricket Valley Energy Center IIGas1.1 GWcompleted2014-06NYISO
Cricket Valley Project (QP444 in NYISO Queue)Gas1.0 GWcompleted2014-12ISONE
Cricket Valley Energy CenterGas1.0 GWwithdrawn2008-09NYISO
Combined Cycle (QP310 in NYISO Queue)Gas1.0 GWwithdrawn2008-09ISONE
Dover NY BESS (NYISO-C24-316)Battery1.0 GWwithdrawn2024-12ISONE
Wingdale Energy CenterGas650 MWwithdrawn2008-09NYISO
East FishkillBattery205 MWactive2020-12NYISO
Highbush Energy StorageBattery200 MWactive2024-08NYISO
Agate Storage ProjectBattery200 MWwithdrawn2021-11NYISO
Overlook StorageBattery199 MWactive2024-10NYISO
Aria Storage 2Battery150 MWactive2024-10NYISO
CBBBattery115 MWwithdrawn2019-10NYISO
Aria Storage 1Battery100 MWactive2024-10NYISO
CBB PARKBattery50 MWwithdrawn2021-01NYISO
Queen CityBattery19 MWwithdrawn2019-06NYISO

Large-load connection requests in this county

Requests to connect large new demand — data centres, industry, electrification — as distinct from generation. 3 recorded here.

RequestCapacityStatusQueueStated end use
1 Gig Data Center East Fishkill, NY1.0 GWactiveNYISODAT
iPark 84 Data Center Interconnection150 MWactiveNYISODAT
GTS Dover EMD Compressor16 MWactiveNYISOnot stated

494 of the 545 large-load requests we hold state no end use at all, so most cannot be attributed to any industry. Where this table says “not stated”, that is the filing’s own silence, not our omission.

How this county ranks

Dutchess County ranks #441 of 1,607 US counties by capacity currently queued, and #6 of 57 in New York.

Other New York counties in the queue

CountyPendingCapacity queued
Kings County72.7 GW
Suffolk County212.5 GW
Genesee County51.2 GW
Franklin County6950 MW
Chautauqua County6881 MW
Montgomery County6790 MW
Steuben County5788 MW
Bronx County5760 MW

Go deeper on Dutchess County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Dutchess County on the map County reports All of New York