Data centers and new power in Schoharie County, NY

220 MW of new power is waiting to connect to the grid in Schoharie County, NY — 2 active requests. Typical wait: 6.2 years. 2 projects are built, 10 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Schoharie County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Schoharie County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Schoharie County right now.

220 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 176,000 homes use.
170 MW
has actually been built
2 projects switched on so far.
6.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 14%
  • Still waiting 14%
  • Withdrawn 71%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Schoharie County.

What kind of power is asking to connect

  • Batteries 91%
  • Solar 9%

By capacity requested. Data as of 14 October 2026.

All the numbers

14 requests ever filed
Pending applications
2
of 14 ever filed
Capacity queued
220 MW
requested, not committed
Already built
170 MW
2 projects connected
Built vs decided
16.7%
10 withdrawn
Median wait
6.2 yr
for applications still pending
Connected capacity
1.1 GW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2170 MW14.3%
Still waiting2220 MW14.3%
Withdrawn10290 MW71.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1200 MW
Solar120 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 14 by size
ProjectTypeCapacityStatusFiledQueue
Wheelhouse Energy StorageBatteries200 MWactive2024-09NYISO
Blenheim Gilboa StorageHydro120 MWcompleted2005-03NYISO
Schoharie HighlandsWind70 MWwithdrawn2007-10NYISO
Line Creek SolarSolar50 MWwithdrawn2019-10NYISO
East Point SolarSolar50 MWcompleted2017-03NYISO
Line Creek ESBatteries30 MWwithdrawn2019-10NYISO
Rock District SolarSolar20 MWactive2016-07NYISO
Sharon SolarSolar20 MWwithdrawn2016-09NYISO
Sunny Knoll SolarSolar20 MWwithdrawn2016-10NYISO
Sharon Springs InterconnectionSolar20 MWwithdrawn2019-05NYISO
Cobleskill SolarSolar20 MWwithdrawn2019-12NYISO
Warner Hill SolarSolar20 MWwithdrawn2020-01NYISO
ELP Middleburgh SolarSolar20 MWwithdrawn2020-09NYISO
Sharon SolarSolar20 MWwithdrawn2015-05NYISO

Big new power users asking to connect

1 on record

Requests to connect large new customers — data centers, factories, electrification — rather than power plants.

RequestCapacityStatusQueueStated use
IGTS Wright EMD Compressor14 MWactiveNYISOnot stated

Most of these filings do not say what the power is for. “Not stated” is the filing's silence, not ours.

How Schoharie County compares

#883 in the US · #34 in NY

Schoharie County ranks #883 of 1,607 US counties by power waiting to connect, and #34 of 57 in New York.

CountyWaitingCapacity queued
Suffolk County273.7 GW
Kings County83.1 GW
Orange County101.6 GW
Ulster County111.3 GW
Steuben County81.3 GW
Dutchess County71.1 GW
Nassau County21.1 GW
Genesee County4926 MW

Common questions about power in Schoharie County

How long does it take to get power for a data center in Schoharie County, NY?

The median wait for a project still in the interconnection queue in Schoharie County is 6.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Schoharie County have reached energization and 10 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Schoharie County, NY?

220 MW is currently requested across 2 active interconnection requests, and 170 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Schoharie County, NY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Schoharie County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Schoharie County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Schoharie County on the map County reports All of New York