Schoharie County, NY interconnection queue
2 interconnection applications are pending in Schoharie County, NY, requesting 220 MW of new generating capacity, as of 15 August 2026. 2 projects have been built here and 10 have been withdrawn since 2005.
Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Schoharie County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Battery | 1 | 200 MW |
| Solar | 1 | 20 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 2 | 170 MW | 14.3% |
| Still pending | 2 | 220 MW | 14.3% |
| Withdrawn | 10 | 290 MW | 71.4% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Wheelhouse Energy Storage | Battery | 200 MW | active | 2024-09 | NYISO |
| Blenheim Gilboa Storage | Hydro | 120 MW | completed | 2005-03 | NYISO |
| Schoharie Highlands | Wind | 70 MW | withdrawn | 2007-10 | NYISO |
| Line Creek Solar | Solar | 50 MW | withdrawn | 2019-10 | NYISO |
| East Point Solar | Solar | 50 MW | completed | 2017-03 | NYISO |
| Line Creek ES | Battery | 30 MW | withdrawn | 2019-10 | NYISO |
| Rock District Solar | Solar | 20 MW | active | 2016-07 | NYISO |
| Sharon Solar | Solar | 20 MW | withdrawn | 2016-09 | NYISO |
| Sunny Knoll Solar | Solar | 20 MW | withdrawn | 2016-10 | NYISO |
| Sharon Springs Interconnection | Solar | 20 MW | withdrawn | 2019-05 | NYISO |
| Cobleskill Solar | Solar | 20 MW | withdrawn | 2019-12 | NYISO |
| Warner Hill Solar | Solar | 20 MW | withdrawn | 2020-01 | NYISO |
| ELP Middleburgh Solar | Solar | 20 MW | withdrawn | 2020-09 | NYISO |
| Sharon Solar | Solar | 20 MW | withdrawn | 2015-05 | NYISO |
Large-load connection requests in this county
Requests to connect large new demand — data centres, industry, electrification — as distinct from generation. 1 recorded here.
| Request | Capacity | Status | Queue | Stated end use |
|---|---|---|---|---|
| IGTS Wright EMD Compressor | 14 MW | active | NYISO | not stated |
494 of the 545 large-load requests we hold state no end use at all, so most cannot be attributed to any industry. Where this table says “not stated”, that is the filing’s own silence, not our omission.
How this county ranks
Schoharie County ranks #883 of 1,607 US counties by capacity currently queued, and #27 of 57 in New York.
Other New York counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Kings County | 7 | 2.7 GW |
| Suffolk County | 21 | 2.5 GW |
| Genesee County | 5 | 1.2 GW |
| Franklin County | 6 | 950 MW |
| Chautauqua County | 6 | 881 MW |
| Dutchess County | 5 | 854 MW |
| Montgomery County | 6 | 790 MW |
| Steuben County | 5 | 788 MW |
Go deeper on Schoharie County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Schoharie County on the map County reports All of New York