Data centers and new power in Oswego County, NY

345 MW of new power is waiting to connect to the grid in Oswego County, NY — 4 active requests. Typical wait: 2.0 years. 3 projects are built, 12 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Oswego County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Oswego County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Oswego County right now.

345 MW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 276,000 homes use.
196 MW
has actually been built
3 projects switched on so far.
2.0 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 16%
  • Still waiting 21%
  • Withdrawn 63%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Oswego County.

What kind of power is asking to connect

  • Batteries 93%
  • Solar 7%

By capacity requested. Data as of 14 October 2026.

All the numbers

19 requests ever filed
Pending applications
4
of 19 ever filed
Capacity queued
345 MW
requested, not committed
Already built
196 MW
3 projects connected
Built vs decided
20.0%
12 withdrawn
Median wait
2.0 yr
for applications still pending
Connected capacity
6.0 GW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3196 MW15.8%
Still waiting4345 MW21.1%
Withdrawn123.6 GW63.2%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries2320 MW
Solar125 MW
Other1—

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Nine Mile Point Station Unit #3Nuclear1.6 GWwithdrawn2008-02NYISO
OswegoHydro1.0 GWwithdrawn2008-10NYISO
Selkirk Shores BESSBatteries300 MWactive2026-09NYISO
Sage Creek SolarSolar250 MWwithdrawn2022-11NYISO
Sage Creek SolarSolar250 MWwithdrawn2023-03NYISO
Independence BESSBatteries200 MWwithdrawn2023-12NYISO
Nine Mile Point UprateNuclear168 MWcompleted2006-05NYISO
FitzPatrick Nuclear UprateNuclear112 MWwithdrawn2009-05NYISO
Galloo Island WindWind110 MWwithdrawn2014-12NYISO
Sithe IndependenceNatural gas27 MWcompleted2018-09NYISO
Oswego Clean EnergySolar25 MWactive2024-09NYISO
Oswego SolarSolar25 MWwithdrawn2023-01NYISO
ELP Granby Solar IIBatteries20 MWactive2022-02NYISO
Lacona SolarSolar20 MWwithdrawn2019-08NYISO
Sithe Independence BESSBatteries20 MWwithdrawn2019-11NYISO

How Oswego County compares

#737 in the US · #29 in NY

Oswego County ranks #737 of 1,607 US counties by power waiting to connect, and #29 of 57 in New York.

CountyWaitingCapacity queued
Suffolk County273.7 GW
Kings County83.1 GW
Orange County101.6 GW
Ulster County111.3 GW
Steuben County81.3 GW
Dutchess County71.1 GW
Nassau County21.1 GW
Genesee County4926 MW

Common questions about power in Oswego County

How long does it take to get power for a data center in Oswego County, NY?

The median wait for a project still in the interconnection queue in Oswego County is 2.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Oswego County have reached energization and 12 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Oswego County, NY?

345 MW is currently requested across 4 active interconnection requests, and 196 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Oswego County, NY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Oswego County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Oswego County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Oswego County on the map County reports All of New York