Data centers and new power in Onondaga County, NY

712 MW of new power is waiting to connect to the grid in Onondaga County, NY — 4 active requests. Typical wait: 0.2 years. 0 projects are built, 17 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Onondaga County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Onondaga County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Onondaga County right now.

712 MW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 570,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
0.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 19%
  • Withdrawn 81%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Onondaga County.

What kind of power is asking to connect

  • Batteries 77%
  • Wind 23%

By capacity requested. Data as of 14 October 2026.

All the numbers

21 requests ever filed
Pending applications
4
of 21 ever filed
Capacity queued
712 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
17 withdrawn
Median wait
0.2 yr
for applications still pending
Connected capacity
398 MW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting4712 MW19.0%
Withdrawn172.2 GW81.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries3550 MW
Wind1162 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Empire State ConnectorOther1.0 GWwithdrawn2015-06NYISO
Clay Energy Storage 1Batteries250 MWactive2026-08NYISO
Icebox Energy StorageBatteries202 MWwithdrawn2023-08NYISO
Cassiopeia Energy CenterBatteries200 MWwithdrawn2023-06NYISO
Gillie Brook SolarSolar200 MWwithdrawn2023-07NYISO
ELP Clay StorageBatteries165 MWwithdrawn2023-02NYISO
Maple Harvest WindWind162 MWactive2024-08NYISO
Clay Energy Storage 2Batteries150 MWactive2026-08NYISO
Warners Road BESSBatteries150 MWactive2026-08NYISO
Eastwater Energy StorageBatteries101 MWwithdrawn2023-09NYISO
Three Rivers Energy StorageBatteries80 MWwithdrawn2022-12NYISO
Syracuse Energy StorageBatteries79 MWwithdrawn2023-03NYISO
Ripley HillWind76 MWwithdrawn2005-03NYISO
Onondaga RenewablesWind47 MWwithdrawn2008-10NYISO
Cayuga Energy StorageBatteries20 MWwithdrawn2008-12NYISO

Big new power users asking to connect

5 on record

Requests to connect large new customers — data centers, factories, electrification — rather than power plants.

RequestCapacityStatusQueueStated use
Micron Fab 3606 MWactiveNYISOnot stated
Micron Fab 2576 MWactiveNYISOM-CH
White Pine Phase 1480 MWactiveNYISOM-CH
Ranalli SuperDC270 MWactiveNYISODAT
OOWWTP Expansion Program50 MWactiveNYISOO

Most of these filings do not say what the power is for. “Not stated” is the filing's silence, not ours.

How Onondaga County compares

#507 in the US · #17 in NY

Onondaga County ranks #507 of 1,607 US counties by power waiting to connect, and #17 of 57 in New York.

CountyWaitingCapacity queued
Suffolk County273.7 GW
Kings County83.1 GW
Orange County101.6 GW
Ulster County111.3 GW
Steuben County81.3 GW
Dutchess County71.1 GW
Nassau County21.1 GW
Genesee County4926 MW

Common questions about power in Onondaga County

How long does it take to get power for a data center in Onondaga County, NY?

The median wait for a project still in the interconnection queue in Onondaga County is 0.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Onondaga County have reached energization and 17 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Onondaga County, NY?

712 MW is currently requested across 4 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Onondaga County, NY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Onondaga County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Onondaga County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Onondaga County on the map County reports All of New York