Data centers and new power in Niagara County, NY

735 MW of new power is waiting to connect to the grid in Niagara County, NY — 5 active requests. Typical wait: 2.1 years. 1 projects are built, 22 withdrawn. Data as of 14 October 2026.

Live here?

How far is it from your house?

Anthropic Lake Mariner, run by AI XPV Platform, is in Niagara County and uses about as much electricity as 34,000 homes.

2 public schools are within 5 miles of it, 2 within one mile. Counted from the facility, not from any home. School list: US Department of Education.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Niagara County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Niagara County right now.

735 MW
of new power is waiting to connect
5 projects asked. Not yet approved. Roughly what 588,000 homes use.
0 MW
has actually been built
1 projects switched on so far.
2.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 4%
  • Still waiting 18%
  • Withdrawn 79%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Niagara County.

What kind of power is asking to connect

  • Batteries 69%
  • Solar 31%

By capacity requested. Data as of 14 October 2026.

All the numbers

28 requests ever filed
Pending applications
5
of 28 ever filed
Capacity queued
735 MW
requested, not committed
Already built
0 MW
1 projects connected
Built vs decided
4.3%
22 withdrawn
Median wait
2.1 yr
for applications still pending
Connected capacity
3.1 GW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built10 MW3.6%
Still waiting5735 MW17.9%
Withdrawn224.3 GW78.6%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries3510 MW
Solar2225 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Riverbank Power AHydro1.0 GWwithdrawn2008-02NYISO
HuntleyNatural gas752 MWwithdrawn2006-07NYISO
SomersetOther687 MWwithdrawn2006-11NYISO
Ridge View Solar Energy CenterSolar350 MWwithdrawn2019-05NYISO
Erie Canal BESSBatteries230 MWactive2024-10NYISO
Erie Canal BESSBatteries230 MWwithdrawn2023-07NYISO
Lighthouse WindWind201 MWwithdrawn2014-06NYISO
BPP NY Somerset BESS IBatteries200 MWwithdrawn2023-09NYISO
Lockport StorageBatteries186 MWwithdrawn2022-08NYISO
Lockport StorageBatteries180 MWactive2024-10NYISO
Niagara Dolomite SolarSolar180 MWwithdrawn2019-05NYISO
FortranOther150 MWwithdrawn2006-03NYISO
Somerset SolarSolar125 MWactive2020-08NYISO
Bear Ridge SolarSolar100 MWactive2018-03NYISO
Buffalo Road Energy StorageBatteries100 MWactive2024-09NYISO

Big new power users asking to connect

8 on record

Requests to connect large new customers — data centers, factories, electrification — rather than power plants.

RequestCapacityStatusQueueStated use
North East Data LLC Data Center500 MWactiveNYISODAT
Somerset Load250 MWenergizedNYISOnot stated
Lake Mariner Data II250 MWactiveNYISODAT-AI
Wulf Compute Data Center II250 MWactiveNYISODAT-AI
Globe Digital Holdings - 1192 MWactiveNYISODAT-AI
Niagara Digital Campus140 MWactiveNYISODAT
Verizon - Project Oasis75 MWactiveNYISOnot stated
Digihost load50 MWenergizedNYISOnot stated

Most of these filings do not say what the power is for. “Not stated” is the filing's silence, not ours.

How Niagara County compares

#498 in the US · #16 in NY

Niagara County ranks #498 of 1,607 US counties by power waiting to connect, and #16 of 57 in New York.

CountyWaitingCapacity queued
Suffolk County273.7 GW
Kings County83.1 GW
Orange County101.6 GW
Ulster County111.3 GW
Steuben County81.3 GW
Dutchess County71.1 GW
Nassau County21.1 GW
Genesee County4926 MW

Common questions about power in Niagara County

How long does it take to get power for a data center in Niagara County, NY?

The median wait for a project still in the interconnection queue in Niagara County is 2.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Niagara County have reached energization and 22 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Niagara County, NY?

735 MW is currently requested across 5 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Niagara County, NY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Niagara County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.