6 interconnection applications are pending in Montgomery County, NY, requesting 790 MW of new generating capacity, as of 15 August 2026. 4 projects have been built here and 22 have been withdrawn since 2004.
Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Montgomery County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Battery | 3 | 550 MW |
| Solar | 2 | 240 MW |
| Other | 1 | — |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 4 | 150 MW | 12.5% |
| Still pending | 6 | 790 MW | 18.8% |
| Withdrawn | 22 | 3.3 GW | 68.8% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| NY Amsterdam 516 Millers Corners Rd Storage | Battery | 430 MW | withdrawn | 2022-11 | NYISO |
| Blue Frost | Battery | 400 MW | withdrawn | 2023-09 | NYISO |
| Blue Frost | Battery | 400 MW | withdrawn | 2023-09 | NYISO |
| Taproot Solar Energy Energy | Solar | 300 MW | withdrawn | 2019-06 | NYISO |
| Flat Creek Storage | Battery | 300 MW | withdrawn | 2023-05 | NYISO |
| Mill Point Solar | Battery | 250 MW | active | 2020-06 | NYISO |
| Taproot Solar | Solar | 205 MW | withdrawn | 2021-02 | NYISO |
| KCE NY 2 | Battery | 200 MW | active | 2018-01 | NYISO |
| Flat Creek Solar | Solar | 200 MW | withdrawn | 2020-09 | NYISO |
| Amsterdam Solar | Solar | 150 MW | active | 2024-10 | NYISO |
| Cherry Valley Solar | Solar | 125 MW | withdrawn | 2022-09 | NYISO |
| OYA Fort Plain Solar | Solar | 115 MW | withdrawn | 2021-03 | NYISO |
| NY Amsterdam 152 Persons Rd Storage | Battery | 115 MW | withdrawn | 2022-10 | NYISO |
| Yellow Feather Energy Center | Solar | 110 MW | withdrawn | 2022-12 | NYISO |
| Mill Point Solar II | Battery | 100 MW | active | 2024-10 | NYISO |
How this county ranks
Montgomery County ranks #473 of 1,607 US counties by capacity currently queued, and #7 of 57 in New York.
Other New York counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Kings County | 7 | 2.7 GW |
| Suffolk County | 21 | 2.5 GW |
| Genesee County | 5 | 1.2 GW |
| Franklin County | 6 | 950 MW |
| Chautauqua County | 6 | 881 MW |
| Dutchess County | 5 | 854 MW |
| Steuben County | 5 | 788 MW |
| Bronx County | 5 | 760 MW |