Lewis County, NY interconnection queue
1 interconnection applications are pending in Lewis County, NY, requesting 125 MW of new generating capacity, as of 15 August 2026. 4 projects have been built here and 16 have been withdrawn since 2003.
Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Lewis County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 1 | 125 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 4 | 264 MW | 19.0% |
| Still pending | 1 | 125 MW | 4.8% |
| Withdrawn | 16 | 1.9 GW | 76.2% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Antelope Energy Storage Center | Battery | 500 MW | withdrawn | 2023-12 | NYISO |
| Chinook Energy Storage Center | Battery | 500 MW | withdrawn | 2023-12 | NYISO |
| Moose Creek 1 | Battery | 130 MW | withdrawn | 2023-12 | NYISO |
| Sugar Maple Solar | Solar | 125 MW | active | 2019-12 | NYISO |
| Number 3 Wind Energy | Wind | 104 MW | completed | 2016-01 | NYISO |
| Bremen Solar | Solar | 102 MW | withdrawn | 2021-11 | NYISO |
| Deer River Wind | Wind | 100 MW | withdrawn | 2016-07 | NYISO |
| New Bremen Solar | Solar | 100 MW | withdrawn | 2019-06 | NYISO |
| Bremen Solar | Solar | 100 MW | withdrawn | 2022-03 | NYISO |
| Roaring Brook | Wind | 80 MW | withdrawn | 2005-07 | NYISO |
| Copenhagen Wind | Wind | 80 MW | completed | 2012-11 | NYISO |
| Roaring Brook Wind | Wind | 80 MW | completed | 2016-05 | NYISO |
| Beaver Falls Energy Storage | Battery | 79 MW | withdrawn | 2023-03 | NYISO |
| Roaring Brook Wind | Wind | 78 MW | withdrawn | 2005-07 | NYISO |
| Twinleaf Solar | Solar | 75 MW | withdrawn | 2021-02 | NYISO |
How this county ranks
Lewis County ranks #1057 of 1,607 US counties by capacity currently queued, and #38 of 57 in New York.
Other New York counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Kings County | 7 | 2.7 GW |
| Suffolk County | 21 | 2.5 GW |
| Genesee County | 5 | 1.2 GW |
| Franklin County | 6 | 950 MW |
| Chautauqua County | 6 | 881 MW |
| Dutchess County | 5 | 854 MW |
| Montgomery County | 6 | 790 MW |
| Steuben County | 5 | 788 MW |
Go deeper on Lewis County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.