Herkimer County, NY interconnection queue

5 interconnection applications are pending in Herkimer County, NY, requesting 100 MW of new generating capacity, as of 15 August 2026. 1 projects have been built here and 22 have been withdrawn since 2004.

Pending applications
5
of 28 ever filed
Capacity queued
100 MW
requested, not committed
Already built
74 MW
1 projects connected
Built vs decided
4.3%
22 withdrawn
Median wait
7.2 yr
for applications still pending
Connected capacity
138 MW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.

What is waiting in Herkimer County, by fuel

FuelProjectsCapacity requested
Solar5100 MW

Outcomes of every application filed here

OutcomeProjectsCapacityShare
Built174 MW3.6%
Still pending5100 MW17.9%
Withdrawn222.3 GW78.6%
Suspended00.0%

Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.

The largest projects on file

ProjectFuelCapacityStatusFiledQueue
Diamond SolarSolar500 MWwithdrawn2022-03NYISO
Columbia Solar Energy CenterSolar350 MWwithdrawn2019-05NYISO
Rocksdrift Energy CenterSolar300 MWwithdrawn2021-06NYISO
Swift SolarBattery300 MWwithdrawn2022-06NYISO
117656 North Creek Solar+StorageBattery207 MWwithdrawn2023-09NYISO
Orion Energy NY IWind100 MWwithdrawn2004-10NYISO
Goldenrod SolarSolar90 MWwithdrawn2018-08NYISO
Little Falls Solar & BESSBattery83 MWwithdrawn2023-02NYISO
Jordanville WindWind80 MWwithdrawn2005-04NYISO
Fairfield Wind ProjectWind74 MWcompleted2004-09NYISO
NY48 - Diamond SolarSolar60 MWwithdrawn2021-05NYISO
Dry Lots WindWind33 MWwithdrawn2011-10NYISO
HelmerBattery21 MWwithdrawn2019-11NYISO
Hills SolarSolar20 MWactive2025-11NYISO
Watkins Rd SolarSolar20 MWactive2016-11NYISO

Large-load connection requests in this county

Requests to connect large new demand — data centres, industry, electrification — as distinct from generation. 2 recorded here.

RequestCapacityStatusQueueStated end use
Incremental Load Request for Remington Factory Redevelopment400 MWactiveNYISODAT
Remington Factory Redevelopment100 MWactiveNYISODAT

494 of the 545 large-load requests we hold state no end use at all, so most cannot be attributed to any industry. Where this table says “not stated”, that is the filing’s own silence, not our omission.

How this county ranks

Herkimer County ranks #1096 of 1,607 US counties by capacity currently queued, and #41 of 57 in New York.

Other New York counties in the queue

CountyPendingCapacity queued
Kings County72.7 GW
Suffolk County212.5 GW
Genesee County51.2 GW
Franklin County6950 MW
Chautauqua County6881 MW
Dutchess County5854 MW
Montgomery County6790 MW
Steuben County5788 MW

Go deeper on Herkimer County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Herkimer County on the map County reports All of New York