Bronx County, NY interconnection queue
5 interconnection applications are pending in Bronx County, NY, requesting 760 MW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 11 have been withdrawn since 1999.
Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Bronx County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Battery | 5 | 760 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 5 | 760 MW | 31.2% |
| Withdrawn | 11 | 3.3 GW | 68.8% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| NY Wind - Mott Haven | Wind | 1.3 GW | withdrawn | 2020-08 | NYISO |
| Oak Point Yard | Gas | 500 MW | withdrawn | 1999-04 | NYISO |
| Blue Spruce Storage | Battery | 300 MW | active | 2024-08 | NYISO |
| Tremont BESS | Battery | 300 MW | withdrawn | 2020-08 | NYISO |
| Bronx Shores Energy Storage | Battery | 300 MW | withdrawn | 2021-12 | NYISO |
| Palladium Storage | Battery | 255 MW | withdrawn | 2023-02 | NYISO |
| Blue Spruce Storage | Battery | 245 MW | withdrawn | 2023-05 | NYISO |
| Clover Leaf Hollers Ave | Gas | 174 MW | withdrawn | 2011-10 | NYISO |
| Palladium Storage | Battery | 140 MW | active | 2024-08 | NYISO |
| Port Morris Energy Storage | Battery | 130 MW | active | 2024-08 | NYISO |
| Harlem River Yards Energy Storage | Battery | 106 MW | withdrawn | 2022-07 | NYISO |
| South Bronx Energy Storage | Battery | 100 MW | active | 2024-09 | NYISO |
| Hell Gate Energy Storage | Battery | 95 MW | withdrawn | 2022-07 | NYISO |
| Hell Gate Energy Storage | Battery | 90 MW | active | 2024-10 | NYISO |
| Gotham Power - Bronx I | Gas | 80 MW | withdrawn | 2000-01 | NYISO |
How this county ranks
Bronx County ranks #485 of 1,607 US counties by capacity currently queued, and #9 of 57 in New York.
Other New York counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Kings County | 7 | 2.7 GW |
| Suffolk County | 21 | 2.5 GW |
| Genesee County | 5 | 1.2 GW |
| Franklin County | 6 | 950 MW |
| Chautauqua County | 6 | 881 MW |
| Dutchess County | 5 | 854 MW |
| Montgomery County | 6 | 790 MW |
| Steuben County | 5 | 788 MW |
Go deeper on Bronx County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.