Data centers and new power in Allegany County, NY

194 MW of new power is waiting to connect to the grid in Allegany County, NY — 2 active requests. Typical wait: 5.2 years. 0 projects are built, 15 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Allegany County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Allegany County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Allegany County right now.

194 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 155,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
5.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 12%
  • Withdrawn 88%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Allegany County.

What kind of power is asking to connect

  • Batteries 52%
  • Solar 48%

By capacity requested. Data as of 14 October 2026.

All the numbers

17 requests ever filed
Pending applications
2
of 17 ever filed
Capacity queued
194 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
15 withdrawn
Median wait
5.2 yr
for applications still pending
Connected capacity
127 MW
indicator, see note

Source: interconnection queues published by NYISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting2194 MW11.8%
Withdrawn15766 MW88.2%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1100 MW
Solar194 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
NYISONYISO cluster request window
Class Year deliverability construct plus the new cluster process.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Nine Mile Wind EnergyWind200 MWwithdrawn2023-05NYISO
Cold Creek SolarBatteries120 MWwithdrawn2021-06NYISO
Nine Mile Wind FarmWind120 MWwithdrawn2022-11NYISO
Zenobe Burns LLCBatteries100 MWactive2024-09NYISO
Allegany WindWind100 MWwithdrawn2016-02NYISO
Alfred Oaks SolarBatteries100 MWwithdrawn2020-09NYISO
Moraine Solar Energy CenterSolar94 MWactive2018-06NYISO
Allegany 2 Battery 2Batteries20 MWwithdrawn2021-01NYISO
Friendship Solar FarmBatteries20 MWwithdrawn2022-09NYISO
Nile Energy Storage ProjectBatteries20 MWwithdrawn2023-02NYISO
Cuba Solar FarmBatteries20 MWwithdrawn2023-08NYISO
Hornell Center 16Solar18 MWwithdrawn2019-06NYISO
Allegany 2 BatteryBatteries10 MWwithdrawn2020-10NYISO
Hornell Center 16 BESSBatteries8 MWwithdrawn2019-07NYISO
Bluejay SolarSolar5 MWwithdrawn2019-08NYISO

How Allegany County compares

#951 in the US · #38 in NY

Allegany County ranks #951 of 1,607 US counties by power waiting to connect, and #38 of 57 in New York.

CountyWaitingCapacity queued
Suffolk County273.7 GW
Kings County83.1 GW
Orange County101.6 GW
Ulster County111.3 GW
Steuben County81.3 GW
Dutchess County71.1 GW
Nassau County21.1 GW
Genesee County4926 MW

Common questions about power in Allegany County

How long does it take to get power for a data center in Allegany County, NY?

The median wait for a project still in the interconnection queue in Allegany County is 5.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Allegany County have reached energization and 15 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Allegany County, NY?

194 MW is currently requested across 2 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Allegany County, NY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New York policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Allegany County — NYISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Allegany County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Allegany County on the map County reports All of New York