Data centers and new power in Texas
463 GW of new power is waiting to connect to the grid in Texas — 1,894 requests across 183 counties, more than any other state. 444 projects are built, 1,084 withdrawn. Data as of 14 October 2026.
What is happening with electricity in Texas
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Texas right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Texas.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
3,612 requests ever filed
Source: the interconnection queues of every transmission provider operating in Texas. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 675 | 162 GW |
| Batteries | 881 | 162 GW |
| Natural gas | 137 | 79.1 GW |
| Wind | 180 | 54.5 GW |
| Solar + battery | 12 | 2.8 GW |
| Nuclear | 1 | 1.3 GW |
| Not stated | 2 | 1.2 GW |
| Other | 4 | 200 MW |
| Oil | 1 | 132 MW |
| Hydro | 1 | 80 MW |
Who runs the waiting list in Texas
Counties in Texas
183 with power on the waiting list
Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.
| County | Waiting | Capacity queued | Already built |
|---|---|---|---|
| Pecos County | 55 | 21.2 GW | 2.2 GW |
| Brazoria County | 55 | 11.7 GW | 2.6 GW |
| Milam County | 33 | 9.2 GW | 548 MW |
| Wharton County | 40 | 9.1 GW | 1.9 GW |
| Jack County | 18 | 8.6 GW | 0 MW |
| Hill County | 23 | 8.0 GW | 1.7 GW |
| Reeves County | 21 | 7.8 GW | 571 MW |
| Wilbarger County | 20 | 7.0 GW | 986 MW |
| Mitchell County | 16 | 6.9 GW | 0 MW |
| San Patricio County | 27 | 6.9 GW | 691 MW |
| Harris County | 31 | 6.8 GW | 1.5 GW |
| Deaf Smith County | 11 | 6.6 GW | 0 MW |
| Matagorda County | 26 | 6.3 GW | 194 MW |
| Zapata County | 27 | 6.3 GW | 239 MW |
| Borden County | 18 | 6.3 GW | 853 MW |
| Cameron County | 27 | 6.1 GW | 585 MW |
| Lamar County | 24 | 6.1 GW | 440 MW |
| Ellis County | 27 | 5.9 GW | 372 MW |
| Upton County | 18 | 5.6 GW | 651 MW |
| Freestone County | 22 | 5.4 GW | 0 MW |
| Bastrop County | 15 | 5.2 GW | 42 MW |
| Bexar County | 22 | 5.2 GW | 188 MW |
| Grimes County | 18 | 5.1 GW | 156 MW |
| Scurry County | 16 | 5.1 GW | 763 MW |
| Hidalgo County | 25 | 4.7 GW | 1.2 GW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| ERCOT | ERCOT Batch 1 large load interconnection - applications not yet dated Successor cycle to Batch Zero under PGRR145. | No date published yet | confirmed source |
| ERCOT | ERCOT generation interconnection — rolling Not FERC-jurisdictional. | Open all year — no cut-off | unconfirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| SPP | SPP 2028 CPP Interconnection Cluster Study (ICS) application window Definitive Interconnection System Impact Study cluster, post Order 2023 compliance. | No date published yet | confirmed source |
| ERCOT | Texas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a)) All new large-load interconnections must carry ERCOT-controlled curtailment equipment. | Open all year — no cut-off | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
Data center campuses recorded in Texas
11 listed
| Campus | Operator | Reported demand |
|---|---|---|
| OpenAI Stargate Abilene | Oracle | 421 MW |
| CoreWeave Denton TX | CoreWeave | 262 MW |
| Meta Temple | Meta | 178 MW |
| Coreweave Helios | CoreWeave | 132 MW |
| Google Midlothian | 103 MW | |
| Google Red Oak | 77 MW | |
| Microsoft SAT40 | Microsoft | 75 MW |
| Microsoft SAT14 | Microsoft | 47 MW |
| Vantage TX1 | 32 MW | |
| Crusoe Abilene Expansion | Microsoft | 0 MW |
| Goodnight | 0 MW |
Tagged as a data center by our classification, not by the operator’s own statement. Only campuses with coordinates can be mapped.