Jack County, TX interconnection queue
18 interconnection applications are pending in Jack County, TX, requesting 8.6 GW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 1 have been withdrawn since 2022.
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Jack County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Gas | 3 | 3.2 GW |
| Battery | 9 | 2.6 GW |
| Solar | 4 | 2.3 GW |
| Wind | 2 | 534 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 18 | 8.6 GW | 90.0% |
| Withdrawn | 1 | 47 MW | 5.0% |
| Suspended | 1 | — | 5.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Thunder Bird 2 Gas | Gas | 1.3 GW | active | 2028-01 | ERCOT |
| Thunder Bird 1 Gas | Gas | 1.3 GW | active | 2030-01 | ERCOT |
| Dovetail Solar 1 | Solar | 666 MW | active | 2024-01 | ERCOT |
| Dovetail Solar 2 | Solar | 666 MW | active | 2024-01 | ERCOT |
| Dovetail Solar 3 | Solar | 666 MW | active | 2024-01 | ERCOT |
| Jack County III – 345 kV | Gas | 660 MW | active | 2026-01 | ERCOT |
| Dovetail Storage | Battery | 509 MW | active | 2024-01 | ERCOT |
| Pinnington Storage | Battery | 503 MW | active | 2024-01 | ERCOT |
| O'Bannion Energy Storage | Battery | 306 MW | active | 2025-01 | ERCOT |
| Wooderson Energy Storage | Battery | 306 MW | active | 2025-01 | ERCOT |
| Fortuna Wind | Wind | 295 MW | active | 2022-01 | ERCOT |
| Possum Kingdom Solar | Solar | 262 MW | active | 2024-01 | ERCOT |
| Campsey Wind | Wind | 238 MW | active | 2023-01 | ERCOT |
| Liberty Senate Energy Storage 1 | Battery | 207 MW | active | 2023-01 | ERCOT |
| Lightning Ridge Energy Storage | Battery | 205 MW | active | 2026-01 | ERCOT |
How this county ranks
Jack County ranks #15 of 1,607 US counties by capacity currently queued, and #5 of 183 in Texas.
Other Texas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
| Mitchell County | 16 | 6.9 GW |
Go deeper on Jack County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.