Data centers and new power in Bexar County, TX

5.2 GW of new power is waiting to connect to the grid in Bexar County, TX — 22 active requests. Typical wait: 2.8 years. 3 projects are built, 1 withdrawn. Data as of 14 October 2026.

Live here?

How far is it from your house?

Microsoft SAT40, run by Microsoft, is in Bexar County and uses about as much electricity as 60,000 homes.

168 public schools are within 5 miles of it, 5 within one mile. Counted from the facility, not from any home. School list: US Department of Education.

Plus 2 more mapped in this county.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Bexar County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Bexar County right now.

5.2 GW
of new power is waiting to connect
22 projects asked. Not yet approved. Roughly what 4.1 million homes use.
188 MW
has actually been built
3 projects switched on so far.
2.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 85%
  • Withdrawn 4%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Bexar County.

What kind of power is asking to connect

  • Batteries 96%
  • Solar 3%
  • Natural gas 1%

By capacity requested. Data as of 14 October 2026.

All the numbers

26 requests ever filed
Pending applications
22
of 26 ever filed
Capacity queued
5.2 GW
requested, not committed
Already built
188 MW
3 projects connected
Built vs decided
75.0%
1 withdrawn
Median wait
2.8 yr
for applications still pending
Connected capacity
5.0 GW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3188 MW11.5%
Still waiting225.2 GW84.6%
Withdrawn145 MW3.8%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries195.0 GW
Solar1152 MW
Natural gas234 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Howard Road BESSBatteries618 MWactive2029-01ERCOT
Orbit Energy StorageBatteries502 MWactive2027-01ERCOT
Bernice Energy StorageBatteries403 MWactive2027-01ERCOT
Mission Station Energy Storage IBatteries375 MWactive2028-01ERCOT
Mission Station Energy Storage IIBatteries375 MWactive2028-01ERCOT
Quela BESSBatteries301 MWactive2022-01ERCOT
Horsepower BESSBatteries258 MWactive2028-01ERCOT
Lavender Storage ProjectBatteries232 MWactive2023-01ERCOT
Taormina StorageBatteries232 MWactive2023-01ERCOT
Ferdinand Grid BESS IIBatteries208 MWactive2027-01ERCOT
Cado StorageBatteries206 MWactive2025-01ERCOT
Caracara Energy Storage CenterBatteries203 MWactive2028-01ERCOT
Padua Grid BESS Unit 3Batteries201 MWactive2028-01ERCOT
RUSH ESSBatteries201 MWactive2026-01ERCOT
Otter BESSBatteries157 MWactive2027-01ERCOT

How Bexar County compares

#51 in the US · #22 in TX

Bexar County ranks #51 of 1,607 US counties by power waiting to connect, and #22 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Bexar County

How long does it take to get power for a data center in Bexar County, TX?

The median wait for a project still in the interconnection queue in Bexar County is 2.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Bexar County have reached energization and 1 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Bexar County, TX?

5.2 GW is currently requested across 22 active interconnection requests, and 188 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Bexar County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Bexar County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Bexar County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Bexar County on the map County reports All of Texas