The rules on data centers in Oregon

1 tracked policy event in Oregon, 1 of them large-load tariff proceeding. 158 large load interconnection requests are recorded here, totalling 21.2 GW. As of 15 September 2026.

In plain words

Oregon is writing new rules about who pays for the power big data centers use. Nothing here bans them. Meanwhile 158 big new power users have asked to connect here. See where they are in Oregon, or check your own address.

Decisions on file
1
bans, new charges, siting rules
Big new power users
158
21.2 GW
Counties involved
30
with power on the waiting list
Who runs the grid here
BPA, IP, PGE, PacifiCorp
read from county coverage

Every decision on file for Oregon

1 tracked
DateLevelWhat happenedCategoryStatus
stateOregon POWER Act (HB 3546): separate rate class for large energy users
Implementation dockets at Oregon PUC through 2026; template for data-center rate separation. source
large-load-tariffimplementing

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

Federal decisions, which apply everywhere

6 items
DateWhat happenedStatus
2026-08-12DOE cancels all three remaining proposed NIETC transmission corridors
Lake Erie–Canada, Southwestern Grid Connector, and Tribal Energy Access corridors cancelled; the federal corridor-designation framework is dead. State siting is now the whole game. source
final
2026-06-18FERC §206 show-cause orders to all six RTOs on large-load integration (EL26-67 through EL26-72)
Every RTO/ISO must justify or reform its large-load interconnection rules. PJM (EL26-67) responses due 2026-08-17; comments due 2026-09-16. Compliance filings will become a primary structured source of load-queue transparency. source
open
2026-03-01FERC further guidance on co-located load interconnection (EL25-49 line of cases)
Follow-on to the Talen–Susquehanna ISA rejection (ER24-2172) and the PJM co-location show-cause; sets the frame for behind-the-meter data centers at generators. source
open
2026-02-12EIA-860S emergency-approved: state air-permit inventory of >1 MW backup generators
New collection motivated by AI data centers; backup-genset permits are the best forthcoming government proxy for data-center locations. EIA also running voluntary DC pilot surveys in TX, WA, NoVA. source
in-effect
2025-10-23FERC opens RM26-4: Interconnection of Large Loads to the Interstate Transmission System
DOE §403 directive forced an expedited rulemaking on large-load interconnection (large load defined >20 MW). ANOPR concepts: 60-day studies, cost allocation, co-location reliability rules. source
open
2024-05-13Order 2023/2023-A generator interconnection reform — cluster transitions ongoing
All ISOs moved to cluster studies with readiness deposits; PJM transition cycles TC1/TC2, ISO-NE first cluster 2026, CAISO Cluster 15. Reshapes every queue metric on this dashboard. source
implementing

Big new power users recorded in Oregon

158 requests

Requests to connect large new customers — data centers, factories, electrification — rather than power plants. Nobody is required to publish these, so what exists publicly is thin: this is what we hold, not what exists.

RequestCountyCapacityStatusQueueStated use
NW Hillsboro-North Plains Semiconductor Plants Project (Phase 2)Washington County1.8 GWactiveBPAnot stated
Pacific West Coast CableColumbia County1.6 GWwithdrawnBPAnot stated
McNary 230 kV SubstationLinn County1.4 GWactiveBPAnot stated
West Hillsboro Data Center Project (Phase 1)Washington County1.4 GWactiveBPAnot stated
Industrial Load Phase 2Morrow County1.2 GWwithdrawnBPAnot stated
Cascade Renewable Transmission Project - HVDCWasco County1.1 GWactiveBPAnot stated
Sixmile Canyon 500kV SubstationUmatilla County1.1 GWwithdrawnBPAnot stated
Six Mile Canyon SubstationUmatilla County1.0 GWactiveBPAnot stated
Keeler SubstationWashington County1.0 GWactiveBPAnot stated
Longhorn 230 kV SubstationLinn County750 MWactiveBPAnot stated
Steelhead 230 kVMorrow County600 MWactiveBPAnot stated
Lochner SubstationLinn County500 MWwithdrawnBPAnot stated
Morrow Flat_LonghornUmatilla County500 MWactiveBPAnot stated
Project Pivot and SpecializedUmatilla County484 MWactiveBPAnot stated
McNary 230kVUmatilla County450 MWactiveBPAnot stated
Stearns LaneWashington County300 MWactiveBPAnot stated
Bonanza Crook County300 MWactiveBPAnot stated
Network Load Expansion 4 Quenett Creek SubstationWasco County300 MWactiveBPAnot stated
Ponderosa SubstationCrook County300 MWwithdrawnBPAnot stated
Network Load Expansion 3Wasco County300 MWactiveBPAnot stated

Most of these filings do not say what the power is for. “Not stated” is the filing's own silence — these rows must not be described as data centers.

Which counties in Oregon this is happening in

top 10 by power requested
CountyWaiting to connectCapacity queued
Sherman County2510.0 GW
Wasco County188.6 GW
Morrow County226.6 GW
Crook County316.3 GW
Klamath County145.3 GW
Jefferson County214.2 GW
Umatilla County173.6 GW
Gilliam County153.2 GW
Lake County212.8 GW
Harney County102.5 GW