Georgia interconnection queue
168 interconnection applications are pending in Georgia, requesting 38.3 GW of new generating capacity across 61 counties, as of 15 August 2026. That places Georgia #10 of 47 states by capacity queued.
Pending applications
168
of 810 ever filed
Capacity queued
38.3 GW
requested, not committed
Already built
14.5 GW
96 connected
Built vs decided
15.8%
510 withdrawn
Counties in the queue
61
with five or more filings
Large load requested
none recorded
0 requests
Source: the interconnection queues of every transmission provider operating in Georgia. Parsed and normalised by Watt Street. Data as of 15 August 2026.
Which queues serve Georgia
What is waiting in Georgia, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 102 | 16.3 GW |
| Gas | 33 | 15.6 GW |
| Battery | 24 | 5.9 GW |
| Nuclear | 8 | 291 MW |
| Other | 1 | 70 MW |
Counties with the most capacity queued
| County | Pending | Capacity queued | Already built |
|---|---|---|---|
| Heard County | 7 | 4.2 GW | 178 MW |
| Bartow County | 7 | 3.6 GW | 0 MW |
| Coweta County | 6 | 2.6 GW | 0 MW |
| Mitchell County | 6 | 2.4 GW | 1.1 GW |
| Monroe County | 1 | 2.0 GW | 218 MW |
| Hancock County | 4 | 2.0 GW | 0 MW |
| Effingham County | 13 | 1.9 GW | 1.1 GW |
| Sumter County | 5 | 1.4 GW | 0 MW |
| Laurens County | 7 | 1.3 GW | 83 MW |
| Jefferson County | 7 | 1.3 GW | 430 MW |
| McDuffie County | 3 | 1.0 GW | 0 MW |
| Putnam County | 2 | 909 MW | 0 MW |
| Glynn County | 3 | 900 MW | 0 MW |
| Washington County | 4 | 688 MW | 650 MW |
| Warren County | 4 | 600 MW | 80 MW |
| Decatur County | 3 | 579 MW | 993 MW |
| Talbot County | 3 | 553 MW | 791 MW |
| Emanuel County | 4 | 538 MW | 0 MW |
| Dodge County | 4 | 510 MW | 0 MW |
| Burke County | 9 | 506 MW | 1.3 GW |
| Floyd County | 4 | 490 MW | 0 MW |
| Baldwin County | 2 | 366 MW | 0 MW |
| Jackson County | 1 | 325 MW | 0 MW |
| Twiggs County | 2 | 322 MW | 200 MW |
| Dougherty County | 2 | 319 MW | 195 MW |
Data centre campuses recorded in Georgia
| Campus | Operator | Reported demand |
|---|---|---|
| Microsoft Fairwater Atlanta | Microsoft | 636 MW |
| CoreWeave Dalton 1 & 2 | CoreWeave | 28 MW |
| xAI QTS Atlanta | SpaceXAI | 17 MW |
A campus is tagged as a data centre by our classification, not by the operator’s own statement. 44 of the 72 campuses we hold carry coordinates, so only those can be mapped.