Floyd County, GA interconnection queue
4 interconnection applications are pending in Floyd County, GA, requesting 490 MW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 10 have been withdrawn since 2019.
Source: interconnection queues published by GTC, SOCO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Floyd County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Battery | 3 | 265 MW |
| Solar | 1 | 225 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 4 | 490 MW | 28.6% |
| Withdrawn | 10 | 3.0 GW | 71.4% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| IC-078 | Gas | 564 MW | withdrawn | — | SOCO |
| IC-113 | Gas | 556 MW | withdrawn | — | SOCO |
| IC-106 | Gas | 508 MW | withdrawn | — | SOCO |
| IC-024 | Gas | 320 MW | withdrawn | — | SOCO |
| Hammond Solar | Solar | 225 MW | active | 2023-09 | GTC |
| IC-823 | Solar | 225 MW | withdrawn | 2019-10 | SOCO |
| IC-824 | Solar | 225 MW | withdrawn | 2019-10 | SOCO |
| 25-IC-1314 | Battery | 192 MW | active | 2025-04 | SOCO |
| IC-1143 | Battery | 175 MW | withdrawn | 2023-05 | SOCO |
| 25-IC-1331 | Battery | 150 MW | withdrawn | 2025-04 | SOCO |
| 25-IC-AP | Battery | 140 MW | withdrawn | — | SOCO |
| IC-1270 | Solar | 100 MW | withdrawn | 2024-03 | SOCO |
| IC-1267 | Battery | 58 MW | active | 2024-03 | SOCO |
| IC-1280 | Battery | 15 MW | active | 2024-04 | SOCO |
How this county ranks
Floyd County ranks #631 of 1,607 US counties by capacity currently queued, and #21 of 61 in Georgia.
Other Georgia counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Heard County | 7 | 4.2 GW |
| Bartow County | 7 | 3.6 GW |
| Coweta County | 6 | 2.6 GW |
| Mitchell County | 6 | 2.4 GW |
| Monroe County | 1 | 2.0 GW |
| Hancock County | 4 | 2.0 GW |
| Effingham County | 13 | 1.9 GW |
| Sumter County | 5 | 1.4 GW |
Go deeper on Floyd County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.