GTC interconnection queue

63 interconnection requests are active in GTC, totalling 12.8 GW, as of 15 August 2026. Of the 107 requests ever filed here, 43 were built and 1 were withdrawn — a build rate of 97.7% on decided applications.

Active requests
63
of 107 ever filed
Capacity queued
12.8 GW
requested, not committed
Built vs decided
97.7%
43 built, 1 withdrawn
Median wait so far
3.1 yr
for requests still active
Median time to build
4.5 yr
request to commercial operation

Source: the GTC interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in GTC, by fuel

FuelProjectsCapacity requested
Solar558.5 GW
Gas43.8 GW
Battery3420 MW
Other170 MW

Where GTC’s queue sits

StateApplicationsCapacity pending
Georgia10512.8 GW

Largest active requests

ProjectFuelCapacityCountyStateFiled
Smarr CCGas2.0 GWMonroe CountyGA2024-08
Flint River 780 MW UnitGas780 MWMitchell CountyGA2024-10
Flint River 2 780 MW UnitGas780 MWMitchell CountyGA2025-03
Pepper Hammock 500 SolarSolar500 MWGlynn CountyGA2022-07
TOCE GA Solar 4Solar325 MWJefferson CountyGA2024-01
Rock House SolarSolar250 MWMcDuffie CountyGA2022-01
Talbot U7Gas250 MWTalbot CountyGA2024-08
Thundering SpringsSolar240 MWLaurens CountyGA2019-11
Hammond SolarSolar225 MWFloyd CountyGA2023-09
Pecan Energy StorageSolar208 MWMitchell CountyGA2023-10
Washington County SolarSolar203 MWWashington CountyGA2024-10
Oakhurst Solar FarmSolar200 MWMitchell CountyGA2017-04
Union City Storage IBattery200 MWFulton CountyGA2019-12
Fairboro SolarSolar200 MWWare CountyGA2021-12
Pepper Hammock SolarSolar200 MWGlynn CountyGA2022-06