Data centers and new power in Tennessee

13.8 GW of new power is waiting to connect to the grid in Tennessee — 53 requests across 24 counties. That is the 34th largest amount of any state. 29 projects are built, 245 withdrawn. Data as of 14 October 2026.

The power picture

What is happening with electricity in Tennessee

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Tennessee right now.

13.8 GW
of new power is waiting to connect
53 projects asked. Not yet approved. Roughly what 11 million homes use.
6.2 GW
has actually been built
29 projects switched on so far.
245
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 9%
  • Still waiting 16%
  • Withdrawn 75%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Tennessee.

What kind of power is asking to connect

  • Natural gas 77%
  • Solar 15%
  • Batteries 5%
  • Hydro 1%
  • Nuclear 1%

By capacity requested. Data as of 14 October 2026.

All the numbers

327 requests ever filed
Waiting to connect
53
of 327 ever filed
Capacity requested
13.8 GW
asked for, not approved
Already built
6.2 GW
29 switched on
Built vs decided
10.6%
245 withdrawn
Counties involved
24
with five or more requests
Big new power users
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Tennessee. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas1510.7 GW
Solar182.1 GW
Batteries6747 MW
Hydro10170 MW
Nuclear4105 MW

Who runs the waiting list in Tennessee

Grid operator or utilityRequestsCapacity pending
TVA32213.7 GW
PJM5100 MW

Counties in Tennessee

24 with power on the waiting list

Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.

CountyWaitingCapacity queuedAlready built
Trousdale County22.4 GW0 MW
Shelby County71.8 GW760 MW
Haywood County31.2 GW1.4 GW
Humphreys County3950 MW350 MW
Fayette County2839 MW0 MW
Hawkins County2325 MW951 MW
Hardeman County1250 MW20 MW
Lawrence County1195 MW0 MW
Lake County3177 MW0 MW
McNairy County2162 MW0 MW
Hamilton County5103 MW4 MW
Maury County1100 MW0 MW
Marion County583 MW4 MW
Anderson County00 MW85 MW
Franklin County00 MW0 MW
Gibson County00 MW0 MW
Grundy County00 MW0 MW
Madison County00 MW0 MW
Montgomery County00 MW0 MW
Obion County00 MW100 MW
Rhea County00 MW1.3 GW
Robertson County00 MW0 MW
Sullivan County00 MW18 MW
Weakley County00 MW600 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

Data center campuses recorded in Tennessee

3 listed
CampusOperatorReported demand
Colossus 2SpaceXAI946 MW
Colossus 1SpaceXAI340 MW
Meta GallatinMeta87 MW

Tagged as a data center by our classification, not by the operator’s own statement. Only campuses with coordinates can be mapped.