New Jersey interconnection queue

40 interconnection applications are pending in New Jersey, requesting 8.1 GW of new generating capacity across 21 counties, as of 15 August 2026. That places New Jersey #35 of 47 states by capacity queued.

Pending applications
40
of 1,315 ever filed
Capacity queued
8.1 GW
requested, not committed
Already built
44.4 GW
254 connected
Built vs decided
20.0%
1,019 withdrawn
Counties in the queue
21
with five or more filings
Large load requested
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in New Jersey. Parsed and normalised by Watt Street. Data as of 15 August 2026.

Which queues serve New Jersey

Queue or utilityApplicationsCapacity pending
PJM1,3078.1 GW
NYISO80 MW

What is waiting in New Jersey, by fuel

FuelProjectsCapacity requested
Gas43.7 GW
Nuclear12.7 GW
Battery131.3 GW
Solar22532 MW

Counties with the most capacity queued

CountyPendingCapacity queuedAlready built
Salem County32.8 GW8.4 GW
Bergen County22.0 GW7.4 GW
Union County21.6 GW9.6 GW
Hudson County2350 MW1.9 GW
Atlantic County3308 MW58 MW
Camden County1300 MW53 MW
Warren County7181 MW555 MW
Mercer County1170 MW17 MW
Cumberland County3149 MW453 MW
Ocean County579 MW2.2 GW
Gloucester County479 MW3.2 GW
Monmouth County235 MW135 MW
Hunterdon County227 MW630 MW
Cape May County120 MW4 MW
Sussex County120 MW101 MW
Burlington County15 MW802 MW
Essex County00 MW2.2 GW
Middlesex County00 MW6.7 GW
Morris County00 MW37 MW
Passaic County00 MW1 MW
Somerset County00 MW4 MW