Gloucester County, NJ interconnection queue
4 interconnection applications are pending in Gloucester County, NJ, requesting 79 MW of new generating capacity, as of 15 August 2026. 13 projects have been built here and 66 have been withdrawn since 1997.
Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Gloucester County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 79 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 13 | 3.2 GW | 15.7% |
| Still pending | 4 | 79 MW | 4.8% |
| Withdrawn | 66 | 9.3 GW | 79.5% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Mickleton 230kV | Gas | 1.3 GW | withdrawn | 2016-10 | PJM |
| Mickleton 230kV | Gas | 1.1 GW | completed | 2014-04 | PJM |
| Mickleton 230kV 2 | Gas | 1.1 GW | withdrawn | 2010-11 | PJM |
| Mickelton 230 kV II | Solar | 869 MW | withdrawn | 2020-09 | PJM |
| Mickleton 230kV 1 | Gas | 860 MW | completed | 2010-11 | PJM |
| Mickleton 230 kV | Gas | 803 MW | withdrawn | 1997-11 | PJM |
| Kearny | Gas | 800 MW | withdrawn | 1997-04 | PJM |
| Eagle Point 230 kV | Gas | 800 MW | withdrawn | 1998-03 | PJM |
| Mickleton 230kV | Gas | 650 MW | completed | 2006-07 | PJM |
| Mickleton 230kV | Gas | 600 MW | withdrawn | 2005-10 | PJM |
| Mickleton 230kV | Gas | 520 MW | withdrawn | 2007-07 | PJM |
| New Freedom - Cardiff 230kV | Gas | 500 MW | withdrawn | 2001-11 | PJM |
| Mickleton 230kV | Gas | 440 MW | withdrawn | 2008-01 | PJM |
| Eagle Point 230kV | Gas | 253 MW | completed | 2012-11 | PJM |
| Bridgeport 230kV | Battery | 225 MW | withdrawn | 2022-02 | PJM |
How this county ranks
Gloucester County ranks #1139 of 1,607 US counties by capacity currently queued, and #11 of 21 in New Jersey.
Other New Jersey counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Salem County | 3 | 2.8 GW |
| Bergen County | 2 | 2.0 GW |
| Union County | 2 | 1.6 GW |
| Hudson County | 2 | 350 MW |
| Atlantic County | 3 | 308 MW |
| Camden County | 1 | 300 MW |
| Warren County | 7 | 181 MW |
| Mercer County | 1 | 170 MW |
Go deeper on Gloucester County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.