Data centers and new power in Mercer County, NJ

170 MW of new power is waiting to connect to the grid in Mercer County, NJ — 1 active requests. Typical wait: 7.0 years. 6 projects are built, 19 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Mercer County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Mercer County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Mercer County right now.

170 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 136,000 homes use.
17 MW
has actually been built
6 projects switched on so far.
7.0 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 23%
  • Still waiting 4%
  • Withdrawn 73%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Mercer County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

26 requests ever filed
Pending applications
1
of 26 ever filed
Capacity queued
170 MW
requested, not committed
Already built
17 MW
6 projects connected
Built vs decided
24.0%
19 withdrawn
Median wait
7.0 yr
for applications still pending
Connected capacity
121 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built617 MW23.1%
Still waiting1170 MW3.8%
Withdrawn19745 MW73.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1170 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Mercer 230kVNatural gas550 MWwithdrawn2000-07PJM
Mercer 230 kVBatteries170 MWactive2019-09PJM
Windsor 230 kVBatteries100 MWwithdrawn2020-01PJM
Pleasant Valley 230 kVSolar20 MWwithdrawn2019-09PJM
Twin Rivers-Windsor 34.5kVSolar13 MWwithdrawn2010-09PJM
Yardville 138kVSolar10 MWwithdrawn2011-04PJM
Lawrence 26kVSolar10 MWwithdrawn2011-04PJM
HightstownSolar10 MWwithdrawn2011-07PJM
Lawrence 26kVSolar9 MWwithdrawn2011-01PJM
Crosswicks 13kVSolar8 MWcompleted2010-04PJM
Princeton University 69 kVSolar5 MWcompleted2020-03PJM
AH2-254Solar5 MWwithdrawn2022-03PJM
Yardville 13kVSolar4 MWwithdrawn2012-02PJM
Laurence 13.2 kVSolar4 MWwithdrawn2018-12PJM
AE2-198Solar3 MWwithdrawn2019-03PJM

How Mercer County compares

#978 in the US · #8 in NJ

Mercer County ranks #978 of 1,607 US counties by power waiting to connect, and #8 of 21 in New Jersey.

CountyWaitingCapacity queued
Salem County32.8 GW
Bergen County22.0 GW
Union County21.6 GW
Hudson County2350 MW
Atlantic County3308 MW
Camden County1300 MW
Warren County7181 MW
Cumberland County3149 MW

Common questions about power in Mercer County

How long does it take to get power for a data center in Mercer County, NJ?

The median wait for a project still in the interconnection queue in Mercer County is 7.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Mercer County have reached energization and 19 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Mercer County, NJ?

170 MW is currently requested across 1 active interconnection requests, and 17 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Mercer County, NJ a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Jersey policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Mercer County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Mercer County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Mercer County on the map County reports All of New Jersey