Data centers and new power in Westmoreland County, VA

16 MW of new power is waiting to connect to the grid in Westmoreland County, VA — 1 active requests. Typical wait: 5.1 years. 5 projects are built, 11 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Westmoreland County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Westmoreland County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Westmoreland County right now.

16 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 13,000 homes use.
79 MW
has actually been built
5 projects switched on so far.
5.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 29%
  • Still waiting 6%
  • Withdrawn 65%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Westmoreland County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

17 requests ever filed
Pending applications
1
of 17 ever filed
Capacity queued
16 MW
requested, not committed
Already built
79 MW
5 projects connected
Built vs decided
31.2%
11 withdrawn
Median wait
5.1 yr
for applications still pending
Connected capacity
56 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built579 MW29.4%
Still waiting116 MW5.9%
Withdrawn11534 MW64.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar116 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Oak Grove – Saunders DP 230 kVSolar100 MWwithdrawn2021-03PJM
Oak Grove – Saunders DP 230 kVSolar100 MWwithdrawn2023-03PJM
Westmoreland - Oak Grove 230 kVSolar80 MWwithdrawn2021-03PJM
Westmoreland – Oak Grove 230 kVSolar80 MWwithdrawn2023-02PJM
Sanders DP - Westmoreland 230 kVSolar65 MWwithdrawn2021-09PJM
Westmoreland 34.5kVSolar20 MWwithdrawn2015-07PJM
Westmoreland 34.5kVSolar20 MWcompleted2016-10PJM
Oak Grove 34.5 kV ISolar20 MWwithdrawn2017-07PJM
Oak Grove 34.5 kV IISolar20 MWwithdrawn2017-07PJM
Oak Grove 34.5 kVSolar20 MWwithdrawn2018-09PJM
Sanders DP 230 kVSolar20 MWcompleted2018-03PJM
Oak Grove 22.9 kVSolar18 MWwithdrawn2021-09PJM
Oak Grove 34.5 kVSolar16 MWactive2021-09PJM
Northern Neck 34.5 kVSolar14 MWcompleted2018-01PJM
Northern Neck 34.5 kVSolar14 MWcompleted2019-09PJM

How Westmoreland County compares

#1229 in the US · #53 in VA

Westmoreland County ranks #1229 of 1,607 US counties by power waiting to connect, and #53 of 71 in Virginia.

Common questions about power in Westmoreland County

How long does it take to get power for a data center in Westmoreland County, VA?

The median wait for a project still in the interconnection queue in Westmoreland County is 5.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 5 projects in Westmoreland County have reached energization and 11 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Westmoreland County, VA?

16 MW is currently requested across 1 active interconnection requests, and 79 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Westmoreland County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Westmoreland County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Westmoreland County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Westmoreland County on the map County reports All of Virginia