Data centers and new power in Brunswick County, VA

3.4 GW of new power is waiting to connect to the grid in Brunswick County, VA — 9 active requests. Typical wait: 5.5 years. 2 projects are built, 24 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Brunswick County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Brunswick County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Brunswick County right now.

3.4 GW
of new power is waiting to connect
9 projects asked. Not yet approved. Roughly what 2.7 million homes use.
1.5 GW
has actually been built
2 projects switched on so far.
5.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 6%
  • Still waiting 26%
  • Withdrawn 69%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Brunswick County.

What kind of power is asking to connect

  • Solar 81%
  • Batteries 19%

By capacity requested. Data as of 14 October 2026.

All the numbers

35 requests ever filed
Pending applications
9
of 35 ever filed
Capacity queued
3.4 GW
requested, not committed
Already built
1.5 GW
2 projects connected
Built vs decided
7.7%
24 withdrawn
Median wait
5.5 yr
for applications still pending
Connected capacity
1.5 GW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built21.5 GW5.7%
Still waiting93.4 GW25.7%
Withdrawn247.3 GW68.6%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar62.7 GW
Batteries3650 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Brunswick 500kVNatural gas3.1 GWwithdrawn2012-10PJM
Carson-Wake 500kVNatural gas1.5 GWcompleted2011-07PJM
Heritage 500 kVSolar1.5 GWactive2025-04PJM
Carson-Wake 500kVNatural gas1.5 GWwithdrawn2023-03PJM
Heritage - Wake 500 kVBatteries500 MWactive2021-03PJM
Heritage - Wake 500 kVSolar400 MWactive2021-03PJM
Carson Rawlings 500kVNot stated315 MWwithdrawn2014-07PJM
Rawlings - Unity 500 kVSolar301 MWactive2021-09PJM
Heritage 500 kVSolar270 MWwithdrawn2021-03PJM
Heritage 500 kVBatteries270 MWwithdrawn2021-03PJM
Heritage - Wake 500 kVSolar250 MWactive2020-12PJM
Brodnax 115 kVSolar200 MWwithdrawn2022-09PJM
Rawlings-Clover 500 kVSolar150 MWwithdrawn2020-09PJM
Rawlings-Clover 500 kVSolar150 MWwithdrawn2020-09PJM
Ebony-Elams Road 115 kVSolar150 MWwithdrawn2020-09PJM

How Brunswick County compares

#97 in the US · #1 in VA

Brunswick County ranks #97 of 1,607 US counties by power waiting to connect, and #1 of 71 in Virginia.

Common questions about power in Brunswick County

How long does it take to get power for a data center in Brunswick County, VA?

The median wait for a project still in the interconnection queue in Brunswick County is 5.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Brunswick County have reached energization and 24 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Brunswick County, VA?

3.4 GW is currently requested across 9 active interconnection requests, and 1.5 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Brunswick County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Brunswick County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Brunswick County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Brunswick County on the map County reports All of Virginia