Data centers and new power in Rockingham County, VA

200 MW of new power is waiting to connect to the grid in Rockingham County, VA — 2 active requests. Typical wait: 7.6 years. 1 projects are built, 21 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Rockingham County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Rockingham County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Rockingham County right now.

200 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 160,000 homes use.
12 MW
has actually been built
1 projects switched on so far.
7.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 4%
  • Still waiting 8%
  • Withdrawn 88%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Rockingham County.

What kind of power is asking to connect

  • Batteries 75%
  • Solar 25%

By capacity requested. Data as of 14 October 2026.

All the numbers

24 requests ever filed
Pending applications
2
of 24 ever filed
Capacity queued
200 MW
requested, not committed
Already built
12 MW
1 projects connected
Built vs decided
4.5%
21 withdrawn
Median wait
7.6 yr
for applications still pending
Connected capacity
243 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built112 MW4.2%
Still waiting2200 MW8.3%
Withdrawn211.2 GW87.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1150 MW
Solar150 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Endless Caverns 115 kVBatteries300 MWwithdrawn2020-09PJM
Endless Caverns 115 kVBatteries150 MWactive2019-05PJM
Harrisonburg - Endless Caverns 230 kVSolar150 MWwithdrawn2021-03PJM
Mount Storm-Valley 500kVWind130 MWwithdrawn2008-07PJM
Harrisonburg 230 kVBatteries100 MWwithdrawn2020-09PJM
North River Delivery Point 115 kVBatteries100 MWwithdrawn2023-04PJM
Harrisburg-Endless Caverns 230 kVSolar73 MWwithdrawn2019-08PJM
North Shenandoah – Merck 115 kVSolar70 MWwithdrawn2021-03PJM
Grottoes-Merck 115kVSolar50 MWactive2018-12PJM
Endless Caverns - Timberville 115 kVSolar38 MWwithdrawn2022-08PJM
AH2-232Batteries25 MWwithdrawn2022-03PJM
Harrisonburg-Stauton 115kVSolar20 MWwithdrawn2015-10PJM
Endless Caverns 34.5 kVSolar20 MWwithdrawn2017-09PJM
Cargill 115 kV (SVEC)Solar20 MWwithdrawn2021-03PJM
TBD 34.5kVSolar20 MWwithdrawn2022-03PJM

How Rockingham County compares

#941 in the US · #33 in VA

Rockingham County ranks #941 of 1,607 US counties by power waiting to connect, and #33 of 71 in Virginia.

Common questions about power in Rockingham County

How long does it take to get power for a data center in Rockingham County, VA?

The median wait for a project still in the interconnection queue in Rockingham County is 7.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Rockingham County have reached energization and 21 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Rockingham County, VA?

200 MW is currently requested across 2 active interconnection requests, and 12 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Rockingham County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Rockingham County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Rockingham County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Rockingham County on the map County reports All of Virginia