Data centers and new power in Prince Edward County, VA

190 MW of new power is waiting to connect to the grid in Prince Edward County, VA — 2 active requests. Typical wait: 5.6 years. 0 projects are built, 10 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Prince Edward County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Prince Edward County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Prince Edward County right now.

190 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 152,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
5.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 17%
  • Withdrawn 83%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Prince Edward County.

What kind of power is asking to connect

  • Batteries 58%
  • Solar 42%

By capacity requested. Data as of 14 October 2026.

All the numbers

12 requests ever filed
Pending applications
2
of 12 ever filed
Capacity queued
190 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
10 withdrawn
Median wait
5.6 yr
for applications still pending
Connected capacity
10 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting2190 MW16.7%
Withdrawn101.0 GW83.3%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1110 MW
Solar180 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 12 by size
ProjectTypeCapacityStatusFiledQueue
Briery-Clover 230kVSolar240 MWwithdrawn2016-10PJM
Clover- Farmville 230kVSolar186 MWwithdrawn2021-09PJM
Madisonville 115 kVSolar150 MWwithdrawn2020-03PJM
Briery-Clover 230 kVSolar150 MWwithdrawn2020-09PJM
Farmville - Moran DP 115 kVSolar125 MWwithdrawn2022-09PJM
Farmville - Moran DP 115 kVBatteries125 MWwithdrawn2022-09PJM
Briery - Finneywood 230 kVBatteries110 MWactive2021-03PJM
Briery - Finneywood 230 kVSolar80 MWactive2021-02PJM
Pamplin – Willis Tap 115 kVSolar20 MWwithdrawn2021-10PJM
Briery Substation 29.4kVSolar20 MWwithdrawn2022-01PJM
Pamplin 34.5kVSolar15 MWwithdrawn2018-03PJM
Briery Substation 29.4kVSolar5 MWwithdrawn2022-01PJM

How Prince Edward County compares

#953 in the US · #34 in VA

Prince Edward County ranks #953 of 1,607 US counties by power waiting to connect, and #34 of 71 in Virginia.

Common questions about power in Prince Edward County

How long does it take to get power for a data center in Prince Edward County, VA?

The median wait for a project still in the interconnection queue in Prince Edward County is 5.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Prince Edward County have reached energization and 10 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Prince Edward County, VA?

190 MW is currently requested across 2 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Prince Edward County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Prince Edward County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Prince Edward County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Prince Edward County on the map County reports All of Virginia