Pittsylvania County, VA interconnection queue
8 interconnection applications are pending in Pittsylvania County, VA, requesting 909 MW of new generating capacity, as of 15 August 2026. 5 projects have been built here and 23 have been withdrawn since 2005.
Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Pittsylvania County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 6 | 754 MW |
| Battery | 2 | 155 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 5 | 396 MW | 13.9% |
| Still pending | 8 | 909 MW | 22.2% |
| Withdrawn | 23 | 2.3 GW | 63.9% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Axton 138 kV | Gas | 530 MW | withdrawn | 2018-09 | PJM |
| Axton 138 kV | Gas | 530 MW | withdrawn | 2018-09 | PJM |
| East Danville-Smith Mountain 138 kV | Solar | 290 MW | withdrawn | 2022-03 | PJM |
| East Danville - Roxborough 230 kV | Solar | 150 MW | active | 2017-12 | PJM |
| Smith Mountain-E. Danville 138 kV | Solar | 150 MW | active | 2018-08 | PJM |
| Banister-Bear Skin 138 kV | Solar | 131 MW | active | 2021-02 | PJM |
| Berry Hill 138 kV | Solar | 125 MW | active | 2019-07 | PJM |
| Smith Mountain-Bearskin 138 kV | Solar | 120 MW | completed | 2017-05 | PJM |
| Smith Mountain-Bearskin 138 kV | Solar | 120 MW | withdrawn | 2023-03 | PJM |
| Hillandale 115kV | Solar | 105 MW | withdrawn | 2022-04 | PJM |
| Grit DP-Perth 115 kV | Solar | 102 MW | active | 2019-03 | PJM |
| Smith Mountain-Bearskin 138kV | Solar | 100 MW | completed | 2016-09 | PJM |
| East Danville 138 kV | Battery | 100 MW | active | 2021-09 | PJM |
| East Danville - Roxborough 230 kV | Solar | 96 MW | active | 2017-12 | PJM |
| East Danville - Roxboro 230 kV | Solar | 96 MW | withdrawn | 2023-02 | PJM |
How this county ranks
Pittsylvania County ranks #411 of 1,607 US counties by capacity currently queued, and #10 of 71 in Virginia.
Other Virginia counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Brunswick County | 9 | 3.4 GW |
| Fluvanna County | 3 | 2.6 GW |
| Sussex County | 7 | 2.5 GW |
| Greensville County | 4 | 1.9 GW |
| Chesterfield County | 9 | 1.5 GW |
| Charlotte County | 6 | 1.4 GW |
| Caroline County | 6 | 1.1 GW |
| Buckingham County | 4 | 996 MW |
Go deeper on Pittsylvania County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Pittsylvania County on the map County reports All of Virginia