Data centers and new power in Campbell County, VA

173 MW of new power is waiting to connect to the grid in Campbell County, VA — 3 active requests. Typical wait: 7.5 years. 3 projects are built, 18 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Campbell County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Campbell County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Campbell County right now.

173 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 138,000 homes use.
200 MW
has actually been built
3 projects switched on so far.
7.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 12%
  • Withdrawn 75%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Campbell County.

What kind of power is asking to connect

  • Solar 65%
  • Batteries 35%

By capacity requested. Data as of 14 October 2026.

All the numbers

24 requests ever filed
Pending applications
3
of 24 ever filed
Capacity queued
173 MW
requested, not committed
Already built
200 MW
3 projects connected
Built vs decided
14.3%
18 withdrawn
Median wait
7.5 yr
for applications still pending
Connected capacity
179 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3200 MW12.5%
Still waiting3173 MW12.5%
Withdrawn18761 MW75.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2113 MW
Batteries160 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Grit DP-Perth 115 kVSolar127 MWwithdrawn2019-03PJM
Red House D.P. 115kVSolar100 MWwithdrawn2021-07PJM
Smith Mountain-Candler's Mountain 138kVSolar80 MWcompleted2016-10PJM
Red House DP - Sugar Hill 115 kVSolar80 MWwithdrawn2022-09PJM
Smith Mountain - Candler Mountain 138 kVSolar80 MWwithdrawn2023-03PJM
Sherwill 69 kVSolar75 MWwithdrawn2020-09PJM
Altavista 115kVBiomass60 MWcompleted2011-04PJM
Smith Mountain-Candler's Mountain 138kVSolar60 MWcompleted2016-10PJM
Gladys DP-Stonemill Switching Station 69 kVSolar60 MWactive2019-03PJM
Gladys DP-Stonemill 69 kVBatteries60 MWactive2020-03PJM
Gladys DP-Stonemill 69 kVBatteries60 MWwithdrawn2021-03PJM
Gladys-Stone Mill 69 kVSolar53 MWactive2019-03PJM
Red House DP 115 kVSolar44 MWwithdrawn2021-09PJM
Red Eye 138 kVBatteries40 MWwithdrawn2021-09PJM
Gladys DP - Stonemill 69 kVBatteries40 MWwithdrawn2021-09PJM

How Campbell County compares

#972 in the US · #35 in VA

Campbell County ranks #972 of 1,607 US counties by power waiting to connect, and #35 of 71 in Virginia.

Common questions about power in Campbell County

How long does it take to get power for a data center in Campbell County, VA?

The median wait for a project still in the interconnection queue in Campbell County is 7.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Campbell County have reached energization and 18 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Campbell County, VA?

173 MW is currently requested across 3 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Campbell County, VA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Virginia policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Campbell County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Campbell County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Campbell County on the map County reports All of Virginia