Data centers and new power in Deschutes County, OR

874 MW of new power is waiting to connect to the grid in Deschutes County, OR — 8 active requests. Typical wait: 1.6 years. 6 projects are built, 41 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Deschutes County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Deschutes County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Deschutes County right now.

874 MW
of new power is waiting to connect
8 projects asked. Not yet approved. Roughly what 699,000 homes use.
46 MW
has actually been built
6 projects switched on so far.
1.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 11%
  • Still waiting 15%
  • Withdrawn 75%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Deschutes County.

What kind of power is asking to connect

  • Solar 69%
  • Geothermal 31%
  • Hydro 0%

By capacity requested. Data as of 14 October 2026.

All the numbers

55 requests ever filed
Pending applications
8
of 55 ever filed
Capacity queued
874 MW
requested, not committed
Already built
46 MW
6 projects connected
Built vs decided
12.8%
41 withdrawn
Median wait
1.6 yr
for applications still pending
Connected capacity
51 MW
indicator, see note

Source: interconnection queues published by BPA, PacifiCorp. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built646 MW10.9%
Still waiting8874 MW14.5%
Withdrawn4112.4 GW74.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar4602 MW
Geothermal2270 MW
Hydro22 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
G1051Solar2.7 GWwithdrawn2023-11BPA
G1052Solar2.7 GWwithdrawn2023-11BPA
G1050Solar1.3 GWwithdrawn2023-11BPA
21-095Solar1.0 GWwithdrawn2021-03PGE
G1056Batteries661 MWwithdrawn2023-11BPA
Duke Energy NANatural gas640 MWwithdrawn2001-12BPA
G0662Solar600 MWwithdrawn2020-12BPA
Ponderosa ProjectSolar600 MWactive2016-05BPA
G0861Wind500 MWwithdrawn2023-04BPA
G0909Solar420 MWwithdrawn2023-07BPA
G0910Solar408 MWwithdrawn2023-07BPA
G0912Solar408 MWwithdrawn2023-07BPA
G0929Solar300 MWwithdrawn2023-09BPA
G1096Geothermal216 MWactive2026-05BPA
G0214Geothermal140 MWwithdrawn2006-01BPA

Big new power users asking to connect

5 on record

Requests to connect large new customers — data centers, factories, electrification — rather than power plants.

RequestCapacityStatusQueueStated use
Midstate LaPine Addition163 MWactiveBPAnot stated
Finley Butte Substation100 MWenergizedBPAnot stated
Sunriver89 MWactiveBPAnot stated
Brother's Tap0 MWactiveBPAnot stated
Yew Ave. Sub0 MWactiveBPAnot stated

Most of these filings do not say what the power is for. “Not stated” is the filing's silence, not ours.

How Deschutes County compares

#435 in the US · #13 in OR

Deschutes County ranks #435 of 1,607 US counties by power waiting to connect, and #13 of 31 in Oregon.

CountyWaitingCapacity queued
Sherman County2611.4 GW
Wasco County188.6 GW
Morrow County226.6 GW
Crook County316.3 GW
Klamath County135.0 GW
Jefferson County214.2 GW
Umatilla County163.5 GW
Gilliam County143.2 GW

Common questions about power in Deschutes County

How long does it take to get power for a data center in Deschutes County, OR?

The median wait for a project still in the interconnection queue in Deschutes County is 1.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Deschutes County have reached energization and 41 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Deschutes County, OR?

874 MW is currently requested across 8 active interconnection requests, and 46 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Deschutes County, OR a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Oregon policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Deschutes County — BPA, PacifiCorp — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Deschutes County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.