Data centers and new power in Posey County, IN

250 MW of new power is waiting to connect to the grid in Posey County, IN — 1 active requests. Typical wait: 4.1 years. 1 projects are built, 10 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Posey County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Posey County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Posey County right now.

250 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 200,000 homes use.
300 MW
has actually been built
1 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 8%
  • Still waiting 8%
  • Withdrawn 83%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Posey County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

12 requests ever filed
Pending applications
1
of 12 ever filed
Capacity queued
250 MW
requested, not committed
Already built
300 MW
1 projects connected
Built vs decided
9.1%
10 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
946 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1300 MW8.3%
Still waiting1250 MW8.3%
Withdrawn102.1 GW83.3%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar1250 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 12 by size
ProjectTypeCapacityStatusFiledQueue
AB Brown 138 kV subNatural gas847 MWwithdrawn2016-09MISO
AB Brown - Gibson 345kV LineSolar300 MWcompleted2019-04MISO
AB Brown 345 - Gibson (Duke Terminal) 345.0kVSolar300 MWwithdrawn2024-04MISO
AB Brown - Farm Bureau 138.0kVSolar250 MWwithdrawn2024-04MISO
AB Brown 345 - Gibson (Duke Terminal) 345.0kVSolar250 MWactive2022-09MISO
AB Brown 345 - Gibson (Duke Terminal) 345.0kVSolar200 MWwithdrawn2024-04MISO
AB Brown 345 - Gibson (Duke Terminal) 345.0kVSolar200 MWwithdrawn2025-03MISO
Point 69kV SubstationSolar + battery100 MWwithdrawn2019-04MISO
Point 69kV SubstationSolar + battery100 MWwithdrawn2019-04MISO
AB Brown 138 kV SubstationNatural gas54 MWwithdrawn2018-03MISO
AB Brown 345 - Gibson (Duke Terminal) 345.0kVSolar45 MWwithdrawn2024-04MISO
AB Brown 345 - Gibson (Duke Terminal) 345.0kVSolar45 MWwithdrawn2024-04MISO

How Posey County compares

#845 in the US · #31 in IN

Posey County ranks #845 of 1,607 US counties by power waiting to connect, and #31 of 57 in Indiana.

CountyWaitingCapacity queued
Sullivan County206.4 GW
Pulaski County103.2 GW
Vermillion County42.4 GW
White County132.1 GW
Fountain County41.4 GW
Blackford County71.3 GW
St. Joseph County41.2 GW
Greene County61.2 GW

Common questions about power in Posey County

How long does it take to get power for a data center in Posey County, IN?

The median wait for a project still in the interconnection queue in Posey County is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Posey County have reached energization and 10 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Posey County, IN?

250 MW is currently requested across 1 active interconnection requests, and 300 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Posey County, IN a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Indiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Posey County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.