Data centers and new power in Blackford County, IN

1.3 GW of new power is waiting to connect to the grid in Blackford County, IN — 7 active requests. Typical wait: 6.6 years. 0 projects are built, 7 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Blackford County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Blackford County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Blackford County right now.

1.3 GW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 1 million homes use.
0 MW
has actually been built
0 projects switched on so far.
6.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 50%
  • Withdrawn 50%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Blackford County.

What kind of power is asking to connect

  • Wind 54%
  • Solar 46%

By capacity requested. Data as of 14 October 2026.

All the numbers

14 requests ever filed
Pending applications
7
of 14 ever filed
Capacity queued
1.3 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
7 withdrawn
Median wait
6.6 yr
for applications still pending

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting71.3 GW50.0%
Withdrawn71.2 GW50.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind4700 MW
Solar3595 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 14 by size
ProjectTypeCapacityStatusFiledQueue
Sorenson-Desoto 345 kVSolar300 MWwithdrawn2020-09PJM
Keystone-Desoto 345 kVSolar245 MWactive2020-03PJM
Desoto - Keystone 345 kVSolar245 MWwithdrawn2023-02PJM
Keystone-Desoto 345 kVSolar200 MWactive2019-09PJM
Keystone-Desoto 345 kVWind200 MWactive2019-09PJM
Sorenson-DeSoto #2 345 kVWind200 MWactive2020-03PJM
Keystone-Desoto 345 kVWind200 MWactive2020-03PJM
Keystone-Desoto 345 kVWind200 MWwithdrawn2023-03PJM
Keystone-Desoto 345 kVWind200 MWwithdrawn2023-03PJM
Jay 138 kVSolar150 MWactive2020-01PJM
Jay-Desoto 138kVSolar150 MWwithdrawn2023-03PJM
Keystone-DeSoto 345 kVWind100 MWactive2020-09PJM
DeSoto-Keystone 345 kVWind100 MWwithdrawn2023-03PJM
Sorenson-DeSoto 345 kVBatteries30 MWwithdrawn2020-09PJM

How Blackford County compares

#294 in the US · #6 in IN

Blackford County ranks #294 of 1,607 US counties by power waiting to connect, and #6 of 57 in Indiana.

CountyWaitingCapacity queued
Sullivan County206.4 GW
Pulaski County103.2 GW
Vermillion County42.4 GW
White County132.1 GW
Fountain County41.4 GW
St. Joseph County41.2 GW
Greene County61.2 GW
Knox County7900 MW

Common questions about power in Blackford County

How long does it take to get power for a data center in Blackford County, IN?

The median wait for a project still in the interconnection queue in Blackford County is 6.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Blackford County have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Blackford County, IN?

1.3 GW is currently requested across 7 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Blackford County, IN a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Indiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Blackford County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.