Greene County, IN interconnection queue
6 interconnection applications are pending in Greene County, IN, requesting 1.2 GW of new generating capacity, as of 15 August 2026. 1 projects have been built here and 6 have been withdrawn since 2019.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Greene County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 730 MW |
| Hybrid | 2 | 425 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 150 MW | 7.7% |
| Still pending | 6 | 1.2 GW | 46.2% |
| Withdrawn | 6 | 1.2 GW | 46.2% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Edwardsport IGCC - Amo 345kV | Hybrid | 300 MW | withdrawn | 2022-09 | MISO |
| Sandborn Primary - Worthington Primary 161.0kV | Hybrid | 300 MW | active | 2025-11 | MISO |
| Edwardsport - Amo 345 kV Line Tap | Solar | 250 MW | withdrawn | 2019-04 | MISO |
| Worthington Primary - Merom Primary 345 kV line | Solar | 240 MW | withdrawn | 2022-09 | MISO |
| Merom Primary - Worthington Primary 345.0kV | Solar | 220 MW | active | 2024-04 | MISO |
| Merom Primary - Worthington Primary 345.0kV | Solar | 200 MW | active | 2022-09 | MISO |
| TH Pfizer Jct. - Worthington (HED) | Solar | 175 MW | withdrawn | 2024-04 | MISO |
| Edwardsport IGCC - Amo 345.0kV | Solar | 160 MW | active | 2022-09 | MISO |
| Worthington Substation 138kV | Solar | 150 MW | completed | 2024-03 | MISO |
| Worthington | Solar | 150 MW | active | 2025-01 | MISO |
| Sanborn - Linton 138 kV Line Tap | Solar | 140 MW | withdrawn | 2019-04 | MISO |
| Sandborn Primary - Worthington Primary 161.0kV | Hybrid | 125 MW | active | 2022-09 | MISO |
| Worthington - Merom 345kV Line | Solar | 80 MW | withdrawn | 2022-09 | MISO |
How this county ranks
Greene County ranks #338 of 1,607 US counties by capacity currently queued, and #8 of 57 in Indiana.
Other Indiana counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Sullivan County | 20 | 6.4 GW |
| Pulaski County | 10 | 3.2 GW |
| Vermillion County | 4 | 2.4 GW |
| White County | 13 | 2.1 GW |
| Fountain County | 4 | 1.4 GW |
| Blackford County | 7 | 1.3 GW |
| St. Joseph County | 4 | 1.2 GW |
| Knox County | 7 | 900 MW |
Go deeper on Greene County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.