1 interconnection applications are pending in Cross County, AR, requesting 200 MW of new generating capacity, as of 15 August 2026. 3 projects have been built here and 11 have been withdrawn since 2018.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Cross County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Wind | 1 | 200 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 3 | 405 MW | 20.0% |
| Still pending | 1 | 200 MW | 6.7% |
| Withdrawn | 11 | 1.8 GW | 73.3% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| AECC WYNNE EAST - PARKIN 161.0kV | Hybrid | 300 MW | withdrawn | 2024-04 | MISO |
| EBONY SS - 5WM LEHI-W | Solar | 250 MW | withdrawn | 2021-11 | MISO |
| Parkin | Wind | 200 MW | active | 2022-09 | MISO |
| AECC WYNNE EAST - PARKIN 161.0kV | Hybrid | 200 MW | withdrawn | 2024-04 | MISO |
| PARKIN - KUHN ROAD 161.0kV | Hybrid | 198 MW | withdrawn | 2024-04 | MISO |
| FISHER - CHERRY VALLEY 161.0kV | Hybrid | 175 MW | withdrawn | 2024-04 | MISO |
| TWIST - PARKIN 161.0kV | Solar | 170 MW | withdrawn | 2024-04 | MISO |
| WYNNE INDUSTRIAL | Solar | 160 MW | withdrawn | 2025-07 | MISO |
| Wynne South - Wynne East AECC 161 kV Line Tap | Solar | 135 MW | completed | 2018-03 | MISO |
| Fisher - Cherry Valley 161kV Line | Solar | 135 MW | withdrawn | 2019-04 | MISO |
| FORREST CITY N SS - WYNNE SOUTH 161.0kV | Wind | 135 MW | completed | 2021-10 | MISO |
| FISHER - CHERRY VALLEY 161.0kV | Solar | 135 MW | completed | 2022-03 | MISO |
| FORREST CITY N SS - WYNNE SOUTH 161.0kV | Wind | 135 MW | withdrawn | 2024-04 | MISO |
| Forrest City to Wynne S 161 KV Line | Wind | 52 MW | withdrawn | 2020-06 | MISO |
| Wynne East to Wynne South 161kV line (J1125 sub) | Solar | 10 MW | withdrawn | 2021-11 | MISO |
How this county ranks
Cross County ranks #905 of 1,607 US counties by capacity currently queued, and #23 of 34 in Arkansas.
Other Arkansas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Crittenden County | 7 | 1.8 GW |
| Mississippi County | 6 | 1.5 GW |
| Jefferson County | 4 | 1.2 GW |
| Jackson County | 4 | 1.2 GW |
| Calhoun County | 3 | 1.1 GW |
| Craighead County | 4 | 950 MW |
| Ouachita County | 4 | 901 MW |
| Phillips County | 6 | 890 MW |
Go deeper on Cross County