PacifiCorp interconnection queue
275 interconnection requests are active in PacifiCorp, totalling 49.0 GW, as of 15 August 2026. Of the 2,160 requests ever filed here, 232 were built and 1,627 were withdrawn — a build rate of 12.5% on decided applications.
Active requests
275
of 2,160 ever filed
Capacity queued
49.0 GW
requested, not committed
Built vs decided
12.5%
232 built, 1,627 withdrawn
Median wait so far
3.2 yr
for requests still active
Median time to build
2.5 yr
request to commercial operation
Source: the PacifiCorp interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.
What is queued in PacifiCorp, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 156 | 27.6 GW |
| Battery | 53 | 8.8 GW |
| Wind | 32 | 6.0 GW |
| Gas | 24 | 5.1 GW |
| Nuclear | 3 | 1.5 GW |
| Geothermal | 4 | 64 MW |
| Hydro | 3 | 9 MW |
Where PacifiCorp’s queue sits
| State | Applications | Capacity pending |
|---|---|---|
| Utah | 867 | 20.7 GW |
| Oregon | 695 | 13.6 GW |
| Wyoming | 332 | 8.6 GW |
| Idaho | 126 | 3.1 GW |
| Montana | 19 | 2.0 GW |
| Washington | 96 | 858 MW |
| California | 19 | 175 MW |
| Arizona | 1 | 0 MW |
| Colorado | 2 | 0 MW |
| New Mexico | 1 | 0 MW |
| Nevada | 2 | 0 MW |
Largest active requests
| Project | Fuel | Capacity | County | State | Filed |
|---|---|---|---|---|---|
| T2-081 | Solar | 1.3 GW | Harney County | OR | 2025-09 |
| T2-082 | Solar | 1.3 GW | Klamath County | OR | 2025-09 |
| C012 | Wind | 750 MW | Wheatland County | MT | 2020-07 |
| T2-070 | Solar | 640 MW | Harney County | OR | 2025-09 |
| C006 | Wind | 600 MW | Wheatland County | MT | 2019-02 |
| C2-45 | Solar | 600 MW | Power County | ID | 2022-04 |
| T2-033 | Gas | 600 MW | Sweetwater County | WY | 2025-09 |
| T2-034 | Gas | 600 MW | Sweetwater County | WY | 2025-09 |
| T2-017 | Gas | 600 MW | Converse County | WY | 2025-08 |
| 838 | Solar | 525 MW | Utah County | UT | 2016-12 |
| C1-35 | Wind | 500 MW | Carbon County | WY | 2021-05 |
| C2-10 | Solar | 500 MW | Salt Lake County | UT | 2022-04 |
| C2-32 | Nuclear | 500 MW | Lincoln County | WY | 2022-04 |
| C3-036 | Solar | 500 MW | Millard County | UT | 2023-05 |
| PIS087 | Solar | 500 MW | Salt Lake County | UT | 2024-09 |