Winkler County, TX interconnection queue
1 interconnection applications are pending in Winkler County, TX, requesting 207 MW of new generating capacity, as of 15 August 2026. 1 projects have been built here and 4 have been withdrawn since 2016.
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Winkler County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Battery | 1 | 207 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 250 MW | 14.3% |
| Still pending | 1 | 207 MW | 14.3% |
| Withdrawn | 4 | 215 MW | 57.1% |
| Suspended | 1 | — | 14.3% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Phoebe Solar | Solar | 250 MW | completed | 2017-01 | ERCOT |
| BRP Volans BESS | Battery | 207 MW | active | 2023-01 | ERCOT |
| Bestla Solar | Solar | 180 MW | suspended | 2017-01 | ERCOT |
| Winkler Solar | Solar | 150 MW | withdrawn | 2016-02 | ERCOT |
| Rosie Solar | Solar | 61 MW | withdrawn | 2022-11 | ERCOT |
| SIXTY SIX Solar | Solar | 4 MW | withdrawn | 2019-06 | ERCOT |
| Bestla Solar | Solar | — | withdrawn | — | ERCOT |
How this county ranks
Winkler County ranks #894 of 1,607 US counties by capacity currently queued, and #165 of 183 in Texas.
Other Texas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Jack County | 18 | 8.6 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
Go deeper on Winkler County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.