Data centers and new power in Tom Green County, TX

2.4 GW of new power is waiting to connect to the grid in Tom Green County, TX — 11 active requests. Typical wait: 1.8 years. 4 projects are built, 8 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Tom Green County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Tom Green County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Tom Green County right now.

2.4 GW
of new power is waiting to connect
11 projects asked. Not yet approved. Roughly what 1.9 million homes use.
658 MW
has actually been built
4 projects switched on so far.
1.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 17%
  • Still waiting 46%
  • Withdrawn 33%
  • Paused 4%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Tom Green County.

What kind of power is asking to connect

  • Batteries 40%
  • Solar 37%
  • Wind 23%

By capacity requested. Data as of 14 October 2026.

All the numbers

24 requests ever filed
Pending applications
11
of 24 ever filed
Capacity queued
2.4 GW
requested, not committed
Already built
658 MW
4 projects connected
Built vs decided
33.3%
8 withdrawn
Median wait
1.8 yr
for applications still pending
Connected capacity
818 MW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4658 MW16.7%
Still waiting112.4 GW45.8%
Withdrawn81.4 GW33.3%
Paused1—4.2%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries5959 MW
Solar4889 MW
Wind2559 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Moon Chapel SolarSolar402 MWactive2029-01ERCOT
Moon Chapel WindWind379 MWactive2027-01ERCOT
Christoval SolarSolar324 MWwithdrawn2021-02ERCOT
Fort Concho Energy storageBatteries251 MWactive2025-01ERCOT
Tango Lily BESSBatteries201 MWactive2025-01ERCOT
Tango Lily SolarSolar201 MWactive2029-01ERCOT
Rambler SolarSolar200 MWcompleted2017-08ERCOT
March Road SolarSolar200 MWwithdrawn2017-11ERCOT
Bravepost SolarSolar200 MWwithdrawn2018-02ERCOT
Angelo SolarSolar195 MWcompleted2018-11ERCOT
Hofbrau BESSBatteries181 MWactive2023-01ERCOT
Water Valley Wind EnergyWind180 MWactive2020-01ERCOT
Knickerbocker Storage IIOther178 MWwithdrawn2022-02ERCOT
Zeppelin Energy StorageBatteries164 MWactive2026-01ERCOT
Dove Creek SolarSolar164 MWactive2026-01ERCOT

How Tom Green County compares

#149 in the US · #60 in TX

Tom Green County ranks #149 of 1,607 US counties by power waiting to connect, and #60 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Tom Green County

How long does it take to get power for a data center in Tom Green County, TX?

The median wait for a project still in the interconnection queue in Tom Green County is 1.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Tom Green County have reached energization and 8 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Tom Green County, TX?

2.4 GW is currently requested across 11 active interconnection requests, and 658 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Tom Green County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Tom Green County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Tom Green County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Tom Green County on the map County reports All of Texas