Data centers and new power in Swisher County, TX

2.2 GW of new power is waiting to connect to the grid in Swisher County, TX — 8 active requests. Typical wait: 2.9 years. 2 projects are built, 16 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Swisher County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Swisher County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Swisher County right now.

2.2 GW
of new power is waiting to connect
8 projects asked. Not yet approved. Roughly what 1.7 million homes use.
1.1 GW
has actually been built
2 projects switched on so far.
2.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 8%
  • Still waiting 31%
  • Withdrawn 62%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Swisher County.

What kind of power is asking to connect

  • Solar 47%
  • Wind 29%
  • Batteries 23%

By capacity requested. Data as of 14 October 2026.

All the numbers

26 requests ever filed
Pending applications
8
of 26 ever filed
Capacity queued
2.2 GW
requested, not committed
Already built
1.1 GW
2 projects connected
Built vs decided
11.1%
16 withdrawn
Median wait
2.9 yr
for applications still pending
Connected capacity
1.1 GW
indicator, see note

Source: interconnection queues published by ERCOT, SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built21.1 GW7.7%
Still waiting82.2 GW30.8%
Withdrawn163.2 GW61.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar41.0 GW
Wind1641 MW
Batteries3504 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Commodus 2 WindWind641 MWactive2029-01ERCOT
Hornet SolarSolar602 MWcompleted2020-02ERCOT
Frye StorageBatteries504 MWactive2022-01ERCOT
Commodus 2 SolarSolar502 MWactive2029-01ERCOT
Frye SolarSolar502 MWcompleted2018-05ERCOT
Comanche Run WindWind500 MWwithdrawn2009-03ERCOT
GEN-2019-064Batteries400 MWwithdrawn2019-05SPP
Wildrose WindWind302 MWwithdrawn2011-04ERCOT
GEN-2015-032Wind300 MWwithdrawn2015-06SPP
Lazarus SolarSolar300 MWwithdrawn2019-12ERCOT
GEN-2011-036Wind270 MWwithdrawn2011-07SPP
Hornet Solar II SLFSolar201 MWactive2025-01ERCOT
Stem SolarSolar200 MWactive2024-01ERCOT
GEN-2022-165Batteries200 MWwithdrawn2023-02SPP
GEN-2023-119Solar200 MWwithdrawn2023-10SPP

How Swisher County compares

#173 in the US · #69 in TX

Swisher County ranks #173 of 1,607 US counties by power waiting to connect, and #69 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Swisher County

How long does it take to get power for a data center in Swisher County, TX?

The median wait for a project still in the interconnection queue in Swisher County is 2.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Swisher County have reached energization and 16 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Swisher County, TX?

2.2 GW is currently requested across 8 active interconnection requests, and 1.1 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Swisher County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Swisher County — ERCOT, SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.