Data centers and new power in Sterling County, TX

1.3 GW of new power is waiting to connect to the grid in Sterling County, TX — 7 active requests. Typical wait: 0.8 years. 2 projects are built, 0 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Sterling County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Sterling County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Sterling County right now.

1.3 GW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 1 million homes use.
124 MW
has actually been built
2 projects switched on so far.
0.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 22%
  • Still waiting 78%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Sterling County.

What kind of power is asking to connect

  • Wind 45%
  • Solar 32%
  • Batteries 23%

By capacity requested. Data as of 14 October 2026.

All the numbers

9 requests ever filed
Pending applications
7
of 9 ever filed
Capacity queued
1.3 GW
requested, not committed
Already built
124 MW
2 projects connected
Built vs decided
100.0%
0 withdrawn
Median wait
0.8 yr
for applications still pending
Connected capacity
1.5 GW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2124 MW22.2%
Still waiting71.3 GW77.8%
Withdrawn00 MW0.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind3575 MW
Solar2412 MW
Batteries2302 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 9 by size
ProjectTypeCapacityStatusFiledQueue
Goat Mountain Wind-RepowerWind303 MWactive2027-01ERCOT
Bob Creek WindWind240 MWactive2027-01ERCOT
Roan Solar Phase 1Solar206 MWactive2029-01ERCOT
Roan Solar Phase 2Solar206 MWactive2029-01ERCOT
Goat Mountain BESSBatteries201 MWactive2026-01ERCOT
BlueBell Solar IISolar115 MWcompleted2018-10ERCOT
Goat Mountain BESS 2Batteries101 MWactive2026-01ERCOT
Capricorn I & III repowerWind32 MWactive2017-01ERCOT
Capricorn IV repowerWind9 MWcompleted2017-08ERCOT

How Sterling County compares

#295 in the US · #108 in TX

Sterling County ranks #295 of 1,607 US counties by power waiting to connect, and #108 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Sterling County

How long does it take to get power for a data center in Sterling County, TX?

The median wait for a project still in the interconnection queue in Sterling County is 0.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Sterling County have reached energization and 0 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Sterling County, TX?

1.3 GW is currently requested across 7 active interconnection requests, and 124 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Sterling County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Sterling County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Sterling County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Sterling County on the map County reports All of Texas