Data centers and new power in Schleicher County, TX

2.3 GW of new power is waiting to connect to the grid in Schleicher County, TX — 11 active requests. Typical wait: 0.8 years. 1 projects are built, 7 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Schleicher County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Schleicher County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Schleicher County right now.

2.3 GW
of new power is waiting to connect
11 projects asked. Not yet approved. Roughly what 1.8 million homes use.
200 MW
has actually been built
1 projects switched on so far.
0.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 5%
  • Still waiting 55%
  • Withdrawn 35%
  • Paused 5%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Schleicher County.

What kind of power is asking to connect

  • Solar 41%
  • Batteries 35%
  • Wind 24%

By capacity requested. Data as of 14 October 2026.

All the numbers

20 requests ever filed
Pending applications
11
of 20 ever filed
Capacity queued
2.3 GW
requested, not committed
Already built
200 MW
1 projects connected
Built vs decided
12.5%
7 withdrawn
Median wait
0.8 yr
for applications still pending
Connected capacity
200 MW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1200 MW5.0%
Still waiting112.3 GW55.0%
Withdrawn71.3 GW35.0%
Paused1—5.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar4926 MW
Batteries5780 MW
Wind2544 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Cold Creek SolarSolar455 MWwithdrawn2022-04ERCOT
Cold Creek Solar 2Solar432 MWactive2026-01ERCOT
Sombrero SolarSolar352 MWactive2025-01ERCOT
Live Oak Wind IIWind303 MWactive2028-01ERCOT
Easy Wind Energy CenterWind241 MWactive2027-01ERCOT
Rockefeller SolarSolar207 MWsuspended2019-10ERCOT
Rockefeller StorageBatteries207 MWactive2022-01ERCOT
Tierra Alta Storage SLFBatteries205 MWwithdrawn2024-12ERCOT
DarmstadtWind201 MWwithdrawn2016-06ERCOT
Easy Battery Energy Storage CenterBatteries200 MWactive2027-01ERCOT
Wilson RanchWind200 MWcompleted2010-12ERCOT
Cold Creek StorageBatteries172 MWwithdrawn2022-04ERCOT
Cold Creek Storage 2Batteries172 MWactive2026-01ERCOT
YELLOW LIGHT SOLARSolar152 MWwithdrawn2019-05ERCOT
Cashel BESSBatteries150 MWactive2027-01ERCOT

How Schleicher County compares

#166 in the US · #65 in TX

Schleicher County ranks #166 of 1,607 US counties by power waiting to connect, and #65 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Schleicher County

How long does it take to get power for a data center in Schleicher County, TX?

The median wait for a project still in the interconnection queue in Schleicher County is 0.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Schleicher County have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Schleicher County, TX?

2.3 GW is currently requested across 11 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Schleicher County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Schleicher County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Schleicher County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Schleicher County on the map County reports All of Texas