Schleicher County, TX interconnection queue
11 interconnection applications are pending in Schleicher County, TX, requesting 2.3 GW of new generating capacity, as of 15 August 2026. 1 projects have been built here and 7 have been withdrawn since 2010.
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Schleicher County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 926 MW |
| Battery | 5 | 780 MW |
| Wind | 2 | 544 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 200 MW | 5.0% |
| Still pending | 11 | 2.3 GW | 55.0% |
| Withdrawn | 7 | 1.3 GW | 35.0% |
| Suspended | 1 | — | 5.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Cold Creek Solar | Solar | 455 MW | withdrawn | 2022-04 | ERCOT |
| Cold Creek Solar 2 | Solar | 432 MW | active | 2026-01 | ERCOT |
| Sombrero Solar | Solar | 352 MW | active | 2025-01 | ERCOT |
| Live Oak Wind II | Wind | 303 MW | active | 2028-01 | ERCOT |
| Easy Wind Energy Center | Wind | 241 MW | active | 2027-01 | ERCOT |
| Rockefeller Solar | Solar | 207 MW | suspended | 2019-10 | ERCOT |
| Rockefeller Storage | Battery | 207 MW | active | 2022-01 | ERCOT |
| Tierra Alta Storage SLF | Battery | 205 MW | withdrawn | 2024-12 | ERCOT |
| Darmstadt | Wind | 201 MW | withdrawn | 2016-06 | ERCOT |
| Easy Battery Energy Storage Center | Battery | 200 MW | active | 2027-01 | ERCOT |
| Wilson Ranch | Wind | 200 MW | completed | 2010-12 | ERCOT |
| Cold Creek Storage | Battery | 172 MW | withdrawn | 2022-04 | ERCOT |
| Cold Creek Storage 2 | Battery | 172 MW | active | 2026-01 | ERCOT |
| YELLOW LIGHT SOLAR | Solar | 152 MW | withdrawn | 2019-05 | ERCOT |
| Cashel BESS | Battery | 150 MW | active | 2027-01 | ERCOT |
How this county ranks
Schleicher County ranks #168 of 1,607 US counties by capacity currently queued, and #65 of 183 in Texas.
Other Texas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Jack County | 18 | 8.6 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
Go deeper on Schleicher County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Schleicher County on the map County reports All of Texas