Data centers and new power in Martin County, TX
492 MW of new power is waiting to connect to the grid in Martin County, TX — 3 active requests. Typical wait: 1.8 years. 0 projects are built, 2 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Martin County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Martin County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Martin County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Martin County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
6 requests ever filed
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still waiting | 3 | 492 MW | 50.0% |
| Withdrawn | 2 | 77 MW | 33.3% |
| Paused | 1 | — | 16.7% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Batteries | 3 | 492 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| ERCOT | ERCOT Batch 1 large load interconnection - applications not yet dated Successor cycle to Batch Zero under PGRR145. | No date published yet | confirmed source |
| ERCOT | ERCOT generation interconnection — rolling Not FERC-jurisdictional. | Open all year — no cut-off | unconfirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| ERCOT | Texas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a)) All new large-load interconnections must carry ERCOT-controlled curtailment equipment. | Open all year — no cut-off | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 6 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Jane Storage Energy Center | Batteries | 241 MW | active | 2026-01 | ERCOT |
| Stewart Grady BESS | Batteries | 150 MW | active | 2025-01 | ERCOT |
| Millennium Energy Storage | Batteries | 103 MW | suspended | 2023-05 | ERCOT |
| Picadillo BESS | Batteries | 101 MW | active | 2024-01 | ERCOT |
| Augustus Solar | Solar | 77 MW | withdrawn | 2023-01 | ERCOT |
| Millennium Energy Storage | Solar | — | withdrawn | — | ERCOT |
How Martin County compares
#633 in the US · #151 in TX
Martin County ranks #633 of 1,607 US counties by power waiting to connect, and #151 of 183 in Texas.
| County | Waiting | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Jack County | 18 | 8.6 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
Common questions about power in Martin County
How long does it take to get power for a data center in Martin County, TX?
The median wait for a project still in the interconnection queue in Martin County is 1.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Martin County have reached energization and 2 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Martin County, TX?
492 MW is currently requested across 3 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Martin County, TX a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Martin County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.